Permit Number: TC-COM-0626-00973
Parcel: 117066950

Address:
45 N 5TH AV

Review Status: In Review

Review Details: COMMERCIAL REVIEW - FULL v.3

Permit Number - TC-COM-0626-00973
Review Name: COMMERCIAL REVIEW - FULL v.3
Review Status: In Review
Review Date Reviewer's Name Type of Review Description Status Comments
10/14/2026 Commercial Electrical Standard APPROVED Electrical (E) Reviewer
Jake Doub; jdoub@safebuilt.com
Discipline Status:Approved As Is
Date Completed: 10/14/2026
10/14/2026 Commercial Mechanical Standard APPROVED Mechanical (M) Reviewer
Jorge Valido; jvalido@safebuilt.com
Discipline Status:Approved As Is
Date Completed: 10/12/2026
N/A Commercial Plumbing Standard IN REVIEW
N/A Bldg Permits - Post Review Express PENDING ASSIGNMENT
N/A Design Review Standard PENDING ASSIGNMENT
N/A Fire New Construction Standard PENDING ASSIGNMENT
N/A Site Zoning Standard PENDING ASSIGNMENT
10/14/2026 Commercial Building Standard REQUIRES RESUBMIT Building (B) Reviewer
Andrew Bevis; abevis@safebuilt.com
Discipline Status:Approved As Is
Date Completed: 10/7/2026


Structural (S) Reviewer
Nicholas Jno-Baptiste; njnobaptiste@safebuilt.com
Discipline Status:Denied
Date Completed: 10/12/2026
1.A1.21 (Site Details) / Information Required.Detail 1 shows a 12" SQ. base plate for the Site Lighting at Grade. Provide
the thickness for the base plate.(RESOLVED)
2.S1.0 (General Structural Notes) / Information Required.Provide components and cladding diagrams and design wind
pressures table applicable to structure for roof and wall surfaces per ASCE 7-16/22 Chapter 30.(RESOLVED)
3.S1.0 (General Structural Notes) / Clarification.The ASCE Hazard Tool (https://ascehazardtool.org/ list Seismic Design
Category C for the project location. Update or provide basis for using Seismic Design Category B.(RESOLVED)
4.S1.4 (Typical Details) / Clarification.Reorient Detail 30 to display all the notes.(RESOLVED)
5.S1.5 (Typical Details) / Information Required.Detail 42 does not provide a detail number for the C8.11.5 beam
connections in Notes 3 and 4. Provide the detail number for these references.(UNRESOLVED)
◦The requested information has not been provided.
6.S2.2 (Level 0.5 Column and Shearwall Plan) / Clarification.Note 3 refers to Typical Column Cross Section as Detail
C1/S1.6. Clarify if this should not be Detail CC1/S1.6. This comment applies to other sheets as well.(UNRESOLVED)
◦The keynote refers to CCX/S1.6, but the SCHEDULES Sheet is S1.09.
7.S2.4 (Level 2 Elevated Concrete Podium Plan) / Confirmation.Confirm the LTX/BX labels/callouts are for existing
beams/lintels.(RESOLVED)
8.S2.8 (Level 2.5 Wall Framing Plan) / Clarification.The plan calls out SW5 and SW6 which have not been provided in
the Shearwall Schedule. Revise plan and/or schedule to provide accurate shearwall callout.(RESOLVED)
9.S2.8 (Level 2.5 Wall Framing Plan) / Clarification.The shearwall near Grid 8 has two (2) callouts. Revise plan to
depict one callout for the shearwall in this location.(RESOLVED)
10.S2.8 (Level 2.5 Wall Framing Plan) / Clarification.The plan cuts Section 222 at the elevator which does not appear to
be the correct detail. Confirm if this is the correct detail at the elevator slab opening. This comment applies to other
sheets as well.(RESOLVED)
11.S2.8 (Level 2.5 Wall Framing Plan) / Clarification.The plan calls out Wall Framing Keynotes 6 and 7 on but does not
list them. Provide these keynotes.(RESOLVED)
12.S2.8 (Level 2.5 Wall Framing Plan) / Clarification.The plan calls out Detail 204 at the CMU between the elevator
openings which does not appear to be the correct detail. Confirm if this is the correct detail between the elevator
openings. This comment applies to other sheets as well.(UNRESOLVED)
◦This section is still cut on sheets S2.09, S2.10, S2.11. Clarify if detail applies at the opening.
13.S2.9 (Level 3 Framing Plan) / Clarification.The plan calls out SW3 which have not been provided in the Shearwall

Schedule. Revise plan and or schedule to provide accurate shearwall callout.(RESOLVED)
14.S2.10 (Level 4 Framing Plan) / Clarification.The plan calls out SW4 which have not been provided in the Shearwall
Schedule. Revise plan and or schedule to provide accurate shearwall callout.(RESOLVED)
15.S2.10 (Level 4 Framing Plan) / Clarification.The plan calls out B4 which have not been provided in the Beam
Schedule. Revise plan and or schedule to provide accurate beam callout.(UNRESOLVED)
◦Callout B4 does not appear to be required at this location. Clarify if a steel beam is required to frame out the
chase.
16.S2.13 (Roof Framing Plan) / Clarification.Plan Note 7 does not appear to be called out at the correct location on the
Roof Framing plan. Revise plan and or note.(UNRESOLVED)
◦The note is still called out at the location. Clarify if an elevator hoist beam is required along the perimeter of the
building.
17.S2.13 (Roof Framing Plan) & S5.0 (Roof Framing Details) / Clarification.The High Elevator Roof Framing Plan depicts
wide flange beams framing to an HSS divider beam, Section 303 is labeled as such but the detail depicts HSS to HSS
connections. Revise plan and or note.(UNRESOLVED)
◦The detail has been updated, however, the section view still depicts an hss beam framing to an hss beam.
18.S6.0 (Stair Plans) / Information Required.The stair plans do not have detail callouts. Provide callouts that match the
plan sheets.(UNRESOLVED)
◦Provide callouts for the details. I.E. 1/S6.00, 2/S6.00, etc.
10/13/2026 Site Engineering Standard REQUIRES RESUBMIT Permit Activity Number: TC-COM-0626-00973 (3rd Review)
Project: NEW GROUND UP HOTEL; 6 STORY BUILDING
Location: 45 N 5TH AV
Review Date: 10/13/2026
Reviewer: John Mounsey – Engineering Associate
Reviewer Contact Information: john.mounsey@tucsonaz.gov

Site Engineering Comments:
1. Site Engineering has completed its review of the submitted plan set and cross-referenced it against the associated development package. However, Site Engineering is unable to grant final approval for Commercial Permit: TC-COM-0626-00973 until the associated revision to Development Package TD-DEV-0626-00166 has received full approval and has been issued. Please resubmit for final approval once the development package has been approved and issued by all applicable reviewers. For final approval - Ensure that all building plans match what is shown in the development package plan set.
10/01/2026 PDSD Application Completeness Express REVIEW COMPLETED