Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.3
Permit Number - TC-COM-0624-01273
Review Name: COMMERCIAL REVIEW - FULL v.3
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/17/2024 | Historic | NOT REQUIRED | Based on staff review of revised plans submitted 10/2/2024, all exterior modifications of doors and windows have been removed from scope of work as per comment response letter and plans. Specifically, Key notes on Sheet A1 Demo Plan submitted 10/2/24 as follows: #2 Existing aluminum storefront window; #3 Existing roll up garage door; #4 Existing roll up serving door and #5 Existing entry door. Keynote on Sheet A2 Floor Plan indicates: #16 Existing rollup door to be sealed shut and have door operating mechanism removed. Door appearance to remain as is and not to be changed in exterior appearance. Based on on exterior modifications and only interior remodel, HPZ review is limited to the exterior. No HPZ review required. Other reviews may proceed. Contact Michael.Taku@tucsonaz.gov |
||
10/17/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
10/17/2024 | Commercial Mechanical | REQUIRES RESUBMIT | 1. Keynote 2/M2 calls for the smoke detector to be located “down stream from filters.” Smoke detectors shall be installed in the return air duct, upstream of any outside air connections. [Second comment: Smoke detectors shall be located upstream of the filters.] [Initial comment: Smoke detectors shall be installed in the return air duct, upstream of any outside air connections, for all air distribution systems moving than 2,000 CFM (See keynote 2, Sheet M2). Reference: Section 606.2.1, IMC 2018, as amended by the City of Tucson.] 2. Your resubmittal did not contain a complete set of construction plans. Please provide a complete set of construction plans along with any applicable documents each time you resubmit until issuance of this permit. |
||
10/17/2024 | Commercial Plumbing | REQUIRES RESUBMIT | 1. The drawing does not call for the gas service pressure to be increased to 2 PSIG and does not show the installation of a pressure regulator downstream of the gas meter and set to deliver an appropriate gas pressure to the gas distribution system. [Second comment: The minimum gas pressure for the specified fryers is 7” H2O. Southwest Gas, the local gas utility, provides natural gas at 7” WG, 2 PSIG, and 5 PSIG. Appliances needing gas service at 7” WG or greater will require a gas meter that delivers at least 2 PSIG gas into a regulator located after the meter set. The total new demand, based on the gas isometric is 540 CFH, not 556 CFH. Reference: Section 402.1, IFGC 2018.] [Initial comment: New gas-fired cooking appliances are scheduled for installation under the Type I hood. Show how the complete natural gas piping system will be modified. Provide a natural gas piping design, including the piping layout on a floor plan and a natural gas schematic showing the sizes, loads and developed lengths of the piping. Reference: Section 107.2.1, IBC 2018.] 2. Your resubmittal did not contain a complete set of construction plans. Please provide a complete set of construction plans along with any applicable documents each time you resubmit until issuance of this permit. |
||
10/07/2024 | PDSD Application Completeness | REVIEW COMPLETED |