Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.3
Permit Number - TC-COM-0624-01115
Review Name: COMMERCIAL REVIEW - FULL v.3
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/01/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
10/01/2024 | Commercial Mechanical | REQUIRES RESUBMIT | 1. The ventilation rate for Group R-2, R-3, and R-4 buildings less than three stories is to be calculated using Equation 4-9, Section 403.3.2.1, IMC 2018. The calculations you have proposed have incorrect arithmetic and you do not cite a source for the calculations. [Second comment: Comment not addressed.] [Initial comment: Assuming that the rooftop heat pumps are new work, provide mechanical ventilation for each apartment. Reference: Section R403.6 (N1103.5), IECC (IRC) 2018.] 2. The new heat pump for unit 2643 is noted both as new and as existing. Unit 2641 shows a new heat pump. The current minimum rating for single-packaged heat pumps is 13.4 SEER2, 6.7 HSPF2 (14 SEER, 8 HSPF). [Second comment: Clarify the status of the rooftop units and their energy efficiencies. The proposed equipment schedules show different SEER values than the HVAC Equipment boxed note and in one area the 2-ton unit is existing and it is new in another note. The 3-ton unit is similarly new in one place and existing in another place.] [Initial comment: Assuming that the rooftop heat pumps are new work, show the complete specifications for each heat pump system, including the SEER and HSPF for each unit, any supplemental heaters, and the air leakage rating of the air handler (ASHRAE Standard 193). Reference: Sections R103.2, R403.7 and R501.5, IECC 2018.] 3. Provide a detail showing how the Broan Make-up Air kit is to be installed. Include the termination of the duct to the outside, the control wiring, and the control sensor location. Reference: Section 304.1, IMC 2018. |
||
09/03/2024 | PDSD Application Completeness | REVIEW COMPLETED |