Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0623-01492
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
06/15/2023 Site Zoning APPROVED
07/03/2023 Bldg Permits - Post Review Express PENDING ASSIGNMENT
06/30/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Activity Number: TC-COM-0623-01492

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.

Structural(S) Reviewer
Daljit Benipal
dbenipal@safebuilt.com
Conditionally Approved
Reason:
Date Completed : 6/29/2023 2:34:27 PM
NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances.


Building(B) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 6/29/2023 2:14:30 AM
1. The plans note that the existing doors in the conference room are to be closed off on the interior side. Clarify what closed off means, it is not clear if these doors are to be locked or if some type of partition is to be installed. Note 28 AD-101a and note 11 on sheet A101a.
2. Correct the exterior door notes on sheet AD-101b that indicate note 6, it appears it should be note 2.
3. Clarify if there is to be an exit sign above the new door 105 outside of the employee break area. This door is not indicated as an exit from the shop. Sheet A-151a.
4. Indicate on the drawings that Fire extinguishers shall be installed in accordance with 2018 IFC section 906.2.
5. Indicate that all interior finishes will be in accordance with 2018 IBC 803.1.


Mechanical(M) Reviewer
Neil Samaan
nsamaan@safebuilt.com
Conditionally Approved
Reason:
Date Completed : 6/15/2023 8:24:13 PM
Approved/subject to field approval


Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Approved
Reason:
Date Completed : 6/26/2023 7:18:11 PM


Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Denied
Reason:
Date Completed : 6/25/2023 1:13:53 PM
First Plumbing Review:
1). Plan page P101B doesn't show any piping illustrations to the eye wash that is shown on plan page A103B
2). Fixture schedule on plan page P-201 needs to include the Eye wash that is shown on plan page A103B -IPC 411
3). The lavatory mixing valve on the fixture schedule on plan page P-201 needs to be ASSE 1070 rated -IPC 419.5
07/03/2023 Fire New Construction REVIEW COMPLETED
06/14/2023 PDSD Application Completeness Express REVIEW COMPLETED