Permit Review Detail
Review Status: Approved
Review Details: COMMERCIAL REVIEW - FULL REVISION v.1
Permit Number - TC-COM-0525-00973
Review Name: COMMERCIAL REVIEW - FULL REVISION v.1
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 12/26/2025 | Commercial Building Standard | APPROVED | Structural (S) Reviewer Andrew Bevis; abevis@safebuilt.com Discipline Status:Approved As Is Date Completed: 12/26/2025 Building (B) Reviewer Andrew Bevis; abevis@safebuilt.com Discipline Status:Approved As Is Date Completed: 12/26/2025 |
||
| 12/26/2025 | Commercial Electrical Standard | APPROVED | Electrical (E) Reviewer Andrew Bevis; abevis@safebuilt.com Discipline Status:Approved As Is Date Completed: 12/26/2025 |
||
| 12/26/2025 | Commercial Mechanical Standard | APPROVED | Mechanical (M) Reviewer Andrew Bevis; abevis@safebuilt.com Discipline Status:Approved As Is Date Completed: 12/26/2025 |
||
| 12/26/2025 | Commercial Plumbing Standard | APPROVED | Plumbing (P) Reviewer Andrew Bevis; abevis@safebuilt.com Discipline Status:Approved As Is Date Completed: 12/26/2025 |
||
| 12/23/2025 | Site Engineering Standard | APPROVED | |||
| 01/14/2026 | Site Zoning Standard | APPROVED | |||
| 01/15/2026 | Water - PDSD Standard | APPROVED | |||
| 01/06/2026 | Outdoor Lighting Standard | NOT REQUIRED | No modifications to the outdoor lighting. | ||
| 01/20/2026 | Bldg Permits - Post Review Express | REVIEW COMPLETED | |||
| 01/14/2026 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 12/23/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |