Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - LIMITED v.1
Permit Number - TC-COM-0524-01032
Review Name: COMMERCIAL REVIEW - LIMITED v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/13/2024 | Commercial Electrical | APPROVED | |||
06/06/2024 | Site Zoning | APPROVED | |||
06/12/2024 | Site Engineering | NOT REQUIRED | |||
06/18/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
06/18/2024 | Commercial Building | REQUIRES RESUBMIT | Please submit your revised documents along with a detailed response letter, which states how all Building Review Section comments were addressed. IBC 105.3 For example, it appears a new counter, sink and cabinetry are being added during this interior Tenant Improvement. 1 Please provide a detailed description of the work involved in this permit’s scope. IBC 105.3 For example, it appears a new counter and sink have been added to this project. 2. Please provide wall assembly information to include the gauge of the metal studs, a stud height chart or ESR# for the metal studs and include connections to the roof framing members. IBC107.2.1 and IBC 1607.15 3. Please amend plans to show the new counter and sink are accessible, meeting the requirements of IBC 1109.3 & 1109.4 and the requirements of 2009 ICC A117.1 4. Please provide plumbing drawings for new sink including the connections to existing plumbing, IBC 107.2.1 Mark Masek Plans Examiner – Building Safety Planning and Development Services | City of Tucson main 520.837.4994 email mark.masek@tucsonaz.gov |
||
06/18/2024 | Commercial Mechanical | REQUIRES RESUBMIT | Provide ventilation calculations for HP-2 to verify that adequate ventilation is being supplied considering the change from office space to a medical procedure room. Reference: Section 403.3.1.1, IMC 2018 and Section 8.1, ASHRAE Standard 170-2017. | ||
06/06/2024 | Fire New Construction | REVIEW COMPLETED | |||
05/31/2024 | PDSD Application Completeness | REVIEW COMPLETED |