Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0523-01381
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/27/2023 | Water - PDSD | APPROVED | |||
06/27/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
06/12/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: TC-COM-0523-01381 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. Structural(S) Reviewer Janet Matz jmatz@safebuilt.com Approved Reason: Date Completed : 6/10/2023 5:39:45 AM Building(B) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 6/10/2023 5:38:45 AM 1. Add to the summary of governing codes on sheet A0.0 the 2018 International Fuel Gas Code. 2. Update the architectural stamp to include the date that the drawings were signed. 3. Provide a life safety/ exit plan on the drawings that indicates the travel distances from the most remote points as well as the occupant loads for the separate areas in accordance with 2018 IBC 1004 and 1017.2. Provide a table layout for the reconfigured dining area to verify the occupancy count. 4. Provide a floor plan for the new canopy area including the tables and other items to be provided. The floor plan on sheet A1.0 only shows the roof structure. Show any new lighting or fans to be installed in the canopy on the reflected ceiling plan sheet A2.0 and on the electrical plans. 5. Indicate the required 12” clearance on the latch side of the door for the new exterior door 101 and the new interior door 100 on the drawings. ICCI A117.1- 2009 figure 404. 6. Indicate on the drawings that Fire extinguishers shall be installed in accordance with 2018 IFC section 906.2. 7. Indicate on the room finish schedule sheet A3.0 that all interior finishes will be in accordance with 2018 IBC 803.1. 8. Provide dimensions and indicate the required clearances for all the plumbing fixtures on the enlarged restroom plan sheet A5.0. Show the location of the restroom accessories. Mechanical(M) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 6/10/2023 5:39:31 AM 1. Provide a mechanical COMcheck or other approved methodology for the project for the new proposed units that is in compliance with the 2018 IECC. Electrical(E) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 6/10/2023 5:39:08 AM 1. The mechanical plans indicate a total of 12 new exterior heaters to be installed in the exterior dining area, not 10. Coordinate the drawings and adjust the plans as needed. 2. Indicate the location of the emergency lighting in the event of a power failure with battery backup in the new kitchen area. 2018 IBC 1008.3.1. 3. Indicate the location of an existing emergency light on the exterior at the exit door for the existing interior dining area on the northwest side of the building to illuminate the landings or indicate new fixtures will be provided. 2018 IBC 1008.3.2 (5). Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 6/10/2023 10:04:13 AM First Plumbing Review: 1). Grease systems & grease interceptors on Plan page P-1.0 need vents to open air -IPC 904.1, 1003.9 2). It appears the outdoor dining area can be closed for weather, how will the patio heater exhaust products of combustion & be provided with combustion air? Plan page P3.0 & M2.0 -IFGC 304, 503.1 |
||
06/08/2023 | Site Engineering | REQUIRES RESUBMIT | See zoning comment | ||
06/06/2023 | Site Zoning | REQUIRES RESUBMIT | ZONING REVIEW TRANSMITTAL FROM: PDSD Zoning Review PROJECT: TC-COM-0523-01381 2900 N. Swan Rd. Unit 100 – C-2 Patio Cover & Cooler Addition (1st Review) TRANSMITTAL: June 06, 2023 Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This site is located in C-2 Zone (UDC 4.7.21). Cultural Use: Government owned and operated only is an allowed use in the zone, (UDC Table 4.8-4), subject to Use Specific Standards 4.9.4.M.1 and 4.9.13.P. 1. The proposed patio cover and cooler are not shown on the approved Development Package (DP) DP21-0285. Per UDC Article 3.3.3.G.2.c A site plan (Development Package) is required for the following types of development: existing development undergoing a change of use, building structure additions, and/or a reconfiguration of an area outside a building. A development package (DP) meeting the requirements of the Checklist for Minor Changes to Commercial/Industrial Sites is required to be submitted and approved. The DP is a separate submittal from the building plans. A revision to DP21-0285 will need to be submitted and approved prior to approval of this building plan. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
06/12/2023 | Fire New Construction | REVIEW COMPLETED | |||
05/26/2023 | PDSD Application Completeness | REVIEW COMPLETED |