Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0523-01358
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/06/2023 | Site Zoning | APPROVED | |||
06/27/2023 | Water - PDSD | APPROVED | |||
06/08/2023 | Site Engineering | NOT REQUIRED | |||
06/27/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
06/09/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: TC-COM-0523-01358 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. Structural(S) Reviewer Janet Matz jmatz@safebuilt.com Conditionally Approved Reason: Date Completed : 6/8/2023 11:38:56 PM no structural work was included in this submittal Building(B) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 6/8/2023 11:37:48 PM 1. Verify the actual cost for the project, the application indicates 18,000.00 which appears to be low based on the submitted drawings. Mechanical(M) Reviewer Janet Matz jmatz@safebuilt.com Approved Reason: Date Completed : 6/8/2023 11:38:21 PM Electrical(E) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 6/8/2023 11:38:10 PM 1. Provide a light in utility room 102 on the plans on sheet E1. Update the IECC compliance calculations to include the new fixture. 2017 NEC 210.70 (C). Plumbing(P) Reviewer Janet Matz jmatz@safebuilt.com Approved Reason: Date Completed : 6/8/2023 11:38:33 PM |
||
05/31/2023 | Fire New Construction | REVIEW COMPLETED | |||
05/25/2023 | PDSD Application Completeness | REVIEW COMPLETED |