Permit Number: TC-COM-0523-01253
Parcel: 12905143A

Review Status: Requires Resubmit

Review Details: COMMERCIAL PDSD SIMPLE REVIEW v.2

Permit Number - TC-COM-0523-01253
Review Name: COMMERCIAL PDSD SIMPLE REVIEW v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
05/25/2023 Bldg Permits - Post Review Express PENDING ASSIGNMENT
05/25/2023 Commercial Electrical REQUIRES RESUBMIT Please address the electrical plan review comments and provide a written response.

1 Locate all the Breaker panels on the power floor plan.

2 Please define “New Ground Array” on the electrical line diagram service grounding system.

3 Panel ‘c’ is shown as a 3 Phase panel and fed by a 3 Phase OCPD in Panel ‘D’. Why is the equipment in between these points 1 Phase?

4 It appears that Panels ‘C’ and ‘D’ are new. Is the equipment fed by these Panels new also? Please indicate this on plan sheet ‘E4’ and the Power floor plan.

5 Some of the electrical equipment descriptions in the panel schedule for panel ‘D’ do not correlate with the ‘EQUIPMENT LIST AND NOMENCLATURE’ shown in plan sheet ‘E4’, and the equipment ‘C’ is duplicated.. Also why is there no account for ‘Crusher #1 and Crusher #2 shown in the panel ‘D’ schedule?

6 Verify load calculations for panel ‘D’. Equipment loads shown in plan sheet ‘E4’ EQUIPMENT LIST and load calculated for panel ‘C’ not including ‘Crusher #1 and Crusher #2, are much higher than the total loads shown in amps for panel ‘D’.

7 Panel ‘A’ schedule shows Equipment ‘A’ identified as ‘SHAKER’ the ‘EQUIPMENT LIST’ on plan sheet ‘E4’ shows Equipment ‘A’ as ‘CRUSHER’, and S’SHAKER’ as ‘I’. Please clarify. And verify that the load calculation is correct. The Max load calculated for this panel shows 55 amps. Why is it being fed by only 40 amps MG output?

Ref; 2018 IBC section 107.2.1, 2017 NEC
05/11/2023 PDSD Application Completeness Express REVIEW COMPLETED Please disregard the first review stating requires resubmit as it was an error.