| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/05/2025 | Commercial Electrical | APPROVED | |||
| 05/13/2025 | Commercial Building | NOT REQUIRED | |||
| 05/05/2025 | Outdoor Lighting | NOT REQUIRED | No modifications to the existing Outdoor Lighting. | ||
| 05/17/2025 | Site Engineering | NOT REQUIRED | |||
| 05/19/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 05/13/2025 | Signs | REQUIRES RESUBMIT | May 9. 2025 2200 N Freeway - TC-COM-0425-00845; COT 535 Replace Electrical Meter and Disconnect Comments: 1. The drawing "Partial Site Plan" (page 2 of 2) notes that the work will be done at an existing electrical installation 1600 feet north of the billboard location. That drawing, and the written scope of work, do not identify the Specifications for the existing Meter Socket and Disconnect. The note just says, "…to be replaced with new (like)." The Panel Schedule "Exist. 206 Panel," identifies that the existing panel is rated at 100 amps. That's the panel located on the billboard, and it is not being replaced. But the cut sheets for the new Milbank meter socket and the Disconnect are both rated 200 amps. What are the specifications for the equipment that is being removed? For three #6 conductors, 100 amps would be sufficient. The proposed equipment must have the same specs as the existing equipment that is being removed. Please provide this information. 2. The drawing "Electrical Service (Exist.)" has two risers with weatherheads, but the written Scope of Work doesn't mention the second riser and weatherhead. If it isn't involved in supplying power to this billboard, it should not be replaced under this permit. Kathi McLaughlin, BRC Reviewer |
||
| 05/19/2025 | Site Zoning | REQUIRES RESUBMIT | Until approved by Signs Zoning cannot approve this plan. | ||
| 05/01/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |