Permit Number: TC-COM-0424-00712
Parcel: 12810054A

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0424-00712
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
05/20/2024 Site Zoning APPROVED
05/22/2024 Water - PDSD APPROVED
05/21/2024 Site Engineering NOT REQUIRED
05/22/2024 Bldg Permits - Post Review PENDING ASSIGNMENT
05/10/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 5/6/2024 11:50:49 AM
1. No structural work being completed.


Building(B) Reviewer
Andrew Bevis
abevis@safebuilt.com
Denied
Reason:
Date Completed : 5/6/2024 11:39:01 AM
1. Sheet A-0.2/Occupant Load: The occupant load calculations provided are incorrect. There are multiple uses provided within the tenant space. (A-3 (Waiting room) & B). Provide a space by space occupant load calculation in accordance
with Table 1004.1.2.

◦ There is a distinct difference between occupancy classification and occupancy use. The exceptions provided in Section 303.1.2 apply to that of classification and the requirements of max. allowable area, height, stories, mixuse requirements and overall classification of the building. So yes, the the waiting room is considered as
business in the overall context of the structure and can comply with the business requirements previously mentioned. However, when calculating occupant loads, one must calculate based on the use of the space. The waiting room's use is assembly and the occupant load must be calculated as such in accordance with Section 1004 and Table 1004.1.2.



Mechanical(M) Reviewer
Andrew Bevis
abevis@safebuilt.com
Denied
Reason:
Date Completed : 5/6/2024 11:45:11 AM
1. General: Prepare mechanical calculations to show that ventilation requirements are met and balanced. Include a ventilation schedule to drawings in accordance with 2018 International Mechanical Code Section 403.1 and Table 403.3.

2. General: Please provide a COMcheck that indicates compliance for new mechanical system and scan that data onto one of the mechanical sheets. This provides evidence the mechanical system is in compliance in accordance with the
2018 IECC Section C403.1.


Electrical(E) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 5/6/2024 11:50:35 AM



Plumbing(P) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 5/6/2024 11:49:38 AM
04/23/2024 Fire New Construction REVIEW COMPLETED
04/23/2024 PDSD Application Completeness REVIEW COMPLETED