Permit Number: TC-COM-0424-00648
Parcel: 13323164A

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0424-00648
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
05/10/2024 Water - PDSD APPROVED
05/13/2024 Bldg Permits - Post Review PENDING ASSIGNMENT
04/26/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Denied
Reason:
Date Completed : 4/25/2024 4:38:44 PM
1. GENERAL - UPDATES: For project updates, please submit sheets with all changes clearly marked in revision clouds. Please provide a written response to each comment; updates without a clear response to all comments may not be reviewed. If you have any questions regarding the comments, you may contact me directly. Updates may result in additional comments.

2. GENERAL - DEFERRED SUBMITTALS [INFORMATION ONLY]: You have requested a deferred submittal for the prefabricated wood roof trusses and the pre-engineered canopy. Please be advised that we will place an Administrative Hold on the Certificate of Occupancy pending the submittal of the deferred structural drawings as a REVISION. All Revision fees will apply.

3. GENERAL - GEOTECHNICAL REPORT: Please provide a copy of the site-specific geotechnical report referenced in the structural general notes, Sheet FSS0. The report should support the appropriateness of the selected foundation system for the project site. All building code references must be updated to the current code adopted by the City.

4. GENERAL - MISSING DOCUMENTS: The structural general notes, Sheet FSS0, refer to Special Inspections outlined in Project Specifications, Appendix B. No such document has been submitted. Per the 2018 International Building Code, Section 1704.3, a complete statement of special inspections must be submitted with the construction documents. Please provide a completed statement of special inspections, including all items outlined in IBC Section 1704.3.1.

5. FSSC - PROJECT ADDRESS: The address provided on Cover Sheet FSSC does not match the project address on the title block. Construction documents are site-specific and it is not permissible to re-use drawings at multiple locations. Please revise the address on the title block to match the address of the building application.

6. FSS0 - CONFLICTING INFORMATION: Under "Canopy Lateral Loads" on structural general notes Sheet FSS0, ultimate wind speed is called out as 115 mph. This conflicts with the general notes provided by the canopy manufacturer on Sheet FSC1.3 that states that canopies are designed for an ultimate wind speed of 103 mph. Please confirm which notes control and revise to resolve this conflict.

7. FSS1 - CONCRETE REINFORCEMENT: The Concrete Tank Foundation Plan calls a 6" reinforced concrete slab with #3 rebar at 24" oc. This area of steel does not meet the minimum area requirements for Temperature and Shrinkage reinforcement called out in ACI 318, Section 24.4.3.2. Please revise the specified reinforcement to meet the ratio of 0.0018 (Area of steel : Area of concrete) for 60 ksi rebar.

8. FSS1 - CONCRETE REINFORCEMENT: The Canopy Foundation Plan calls a 5" reinforced concrete slab with #3 rebar at 24" oc. This area of steel does not meet the minimum area requirements for Temperature and Shrinkage reinforcement called out in ACI 318, Section 24.4.3.2. Please revise the specified reinforcement to meet the ratio of 0.0018 (Area of steel : Area of concrete) for 60 ksi rebar.


Building(B) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 4/19/2024 9:34:03 AM
1. General: Include the details showing compliance with the envelope and the mechanical provisions of the 2018 IECC
sections C402, C403.
2. Sheet FSCS: If all canopy documents are included in the construction drawings, please remove the Fuel Station
Canopy from the list as a deferred submittal. (2018 IBC section 107)
3. Sheet FSCS: Include a scope of work, if fire alarms are being installed, and the allowed vs actual area, height, and number of stories. (2018 IBC sections 107, 501, 504, 506)

4. Sheet FSA5: Show the accessible route, maneuvering clearances, signage, and accessible service counter details. Include the dimensions of the maneuvering clearance area in front of the toilet room doors. (2018 IBC section 107, 1104, 1109.12, 1111, 2009 ICC A117.1 sections 402, 403, 404, 404.2.3.2, 703, 904)


Mechanical(M) Reviewer
Jorge Valido
jvalido@safebuilt.com
Denied
Reason:
Date Completed : 4/25/2024 8:32:21 PM
1. General - Provide Ventilation Calculation/Schedule - 2018 IMC Section Table 403.3.1.1

2. General - Provide location of cooler condensers - 2018 IBC Section [A]107.2.1Information on construction documents.

3. General - Provide tie down and Seismic/Wind Restraint detail for the Cooler Condensers - 2018 IMC Section Section 301.15 Wind resistance and Section 301.18 Seismic resistance.

4. General - Provide Roof Plan. Show clear dimensions of serviceable equipment from edge of building. Show clear dimensions from outside air intakes to exhaust outlets. - 2018 IMC Section [BE]304.11Guards

5. General - Provide ComCheck Mechanical Compliance Certificate or other Approved/Certified program. - 2018 IECC Section C403.1.1 Calculations of heating and cooling loads. and C403.2.3 HVAC equipment performance requirements.



Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Denied
Reason:
Date Completed : 4/15/2024 9:55:50 AM
1. Missing electrical FSISD1 ISD PLAN that is shown on Drawing Index on FSCS Cover Sheet. Submit sheet or confirm that it is not needed.



Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Denied
Reason:
Date Completed : 4/16/2024 10:04:33 PM
First Plumbing Review:
1)..General: Plumbing plans and or any any plan pages not uploaded to document files. Please upload plan sets for review: - IPC 2018 106.3.1
05/13/2024 Site Engineering REQUIRES RESUBMIT See zoning comment.

Mike Ortiz
michael.ortiz@tucsonaz.gov
05/13/2024 Site Zoning REQUIRES RESUBMIT ZONING REVIEW TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT:
TC-COM-0424-00648 - TD-DEV-0524-00143
7150 E SPEEDWAY BL. – PAD-3
Fuel Station @ Walmart (1st Review)

TRANSMITTAL DATE: May 13, 2024

DUE DATE: May 11, 2024

Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This site is located in the P-I zone (UDC 4.7.29). Automotive Minor is a allowed use in the zone (UDC Table 4.8-5), subject to Use Specific 4.9.13.E.

1. As Development Package (DP) TD-DEV-0524-00143 has not completed it’s first review Zoning cannot review for compliance and will review the building plans on the next submittal.

2. Zoning cannot approve the building plans until the DP is approved by all review agencies.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.
04/16/2024 Fire New Construction REVIEW COMPLETED
04/11/2024 PDSD Application Completeness REVIEW COMPLETED