Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0423-01017
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/09/2023 | Commercial Electrical | APPROVED | |||
05/01/2023 | Site Zoning | APPROVED | |||
05/11/2023 | Commercial Mechanical | NOT REQUIRED | |||
05/11/2023 | Commercial Plumbing | NOT REQUIRED | |||
05/01/2023 | Site Engineering | NOT REQUIRED | |||
05/15/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
05/15/2023 | Commercial Structural | REQUIRES RESUBMIT | Aloha Vince, The Certificate of Occupancy still would have to be clear as to which area is occupied by each tenant reflecting what the property lease they agreed upon. The lease probably does not show mixed/combined dining spaces. Each business are still separate from each other legally. Each must still have a c of o that reflects legally what they can claim. Therefore, please make the necessary corrections below: 1. I noticed that you have submitted a totally separate permit application for Blind Pig, meaning you are applying for a c of o for it showing a floor plan that shows the wall being removed between the two restaurants. 2. Similarly with Pho Saigon. 3. NOT USED 4. Show an imaginary demarcation dashed line between the two restaurants (you can point to the dotted line where the new opening is located. 5. The previous permit for Blind Pig from 2019 shows a dining occupant load of 541/15=33. Reflect this within the area below the demarcation line. 6. Above the demarcation line show 1233/15=81 7. In the Code Analysis, please show the following: 4. Occupant Load for Tenant Spaces (remove the word "combined" = 176 O.L.) REMOVE Blind Pig kitchen/services no change 1222/200=7 O.L. (keep Existing Pho Saigon Kitchen.......=6 O.L.) (ADD) EXISTING BLIND PIG DINING ROOM 492/15=33 O.L. NEW COMBINED DINING ROOM 492/15=33 O.L. BLIND PIG + 220/15=81 O.L. PHO SAIGON = 114 TOTAL (keep Existing Pho Saigon dining room = 49 O.L.) (REMOVE Existing Outdoor Patios = 106 O.L.) (ADD) EXISTING pHO sAIGON OUTDOOR PATIO .......=40 8. Now that the resources of both restaurants are co-mingled. You will have to somehow make some changes to the sprinkler system, the fire alarm, etc. You cannot have the situation where the fire alarm goes off on the Blind Pig and the Pho Saigon does not go off. Similarly, the fire alarm might go off on the Pho side and not on the Blind Pig side, they would have to be interconnected as called for by the building code. Please submit to the fire department regarding these changes for their review and approval and inspection. 9. Please resubmit. | ||
04/17/2023 | Fire New Construction | REVIEW COMPLETED | |||
04/12/2023 | PDSD Application Completeness | REVIEW COMPLETED |