Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0423-00967
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/05/2023 | Commercial Structural | APPROVED | |||
05/04/2023 | Commercial Electrical | NOT REQUIRED | |||
05/08/2023 | Commercial Mechanical | NOT REQUIRED | |||
05/08/2023 | Commercial Plumbing | NOT REQUIRED | |||
05/08/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
05/02/2023 | Site Engineering | REQUIRES RESUBMIT | See zoning comment | ||
05/02/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: Paul Camarena PDSD Zoning Review Section PROJECT: TC-COM-0423-00967 101 W 6TH ST Zoning C-3 TRANSMITTAL DATE:May 2, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1.COMMENT: Per UDC Article 3.3.3.G.2.c A site plan (Development Package) is required for the following types of development: Existing development undergoing a change of use, building structure additions, and/or a reconfiguration of an area outside a building. A development package (DP) meeting the requirements of Administrative Manual (AM) 2-06 must be submitted and approved prior to approval of this building plan. The DP is a separate submittal from the building plans and is submitted at: https://tdc-online.tucsonaz.gov/#/ The DP will need to be approved prior to approval of this building permit. If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
||
05/03/2023 | Fire New Construction | REVIEW COMPLETED | |||
04/07/2023 | PDSD Application Completeness | REVIEW COMPLETED |