Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0325-00425
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/20/2025 | Commercial Building Standard | APPROVED | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Approved Reason: Date Completed : 3/18/2025 8:21:07 PM Building(B) Reviewer Janet Matz jmatz@safebuilt.com Approved Reason: Date Completed : 3/20/2025 2:00:13 AM |
||
| 03/20/2025 | Commercial Plumbing Standard | APPROVED | Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Approved Reason: Date Completed : 3/8/2025 8:00:12 AM |
||
| 03/25/2025 | Site Zoning Standard | APPROVED | |||
| 03/25/2025 | Water - PDSD Standard | APPROVED | |||
| 04/01/2025 | Site Engineering Standard | NOT REQUIRED | |||
| 04/01/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 03/20/2025 | Commercial Electrical Standard | REQUIRES RESUBMIT | Electrical(E) Reviewer Ron Ross rross@safebuilt.com Denied Reason: Date Completed : 3/11/2025 5:55:01 PM 1. E1.0 LIGHTING NOTES AND DETAILS: Lighting Keynotes Hexagons are too dark and #s cannot be easily seen. Comment applies to lighting sheets too. This will affect the field drawings if sheets are printed out on smaller sheets at smaller scales. 2. E2.1 WEST POWER PLAN: drawing has some CAD artifacts just outside of the bathrooms that should be removed. 3. E2.2 EAST POWER PLAN: Should identify panels shown on E3.0 Electric Service Diagram. 4. E3.0 ELECTRICAL SCHEDULES: 208 Volt ATS is erroneously attached to 480 volt panel. Need to tie ATS into correct panel. If the intent is to provide back up to the entire facility, should select a 480 Volt generator and 480 Volt ATS. 5. E4.0 ELECTRICAL NOTES: Suggestion only, E4.0 should be an electrical cover sheet ie Sheet E0.0. |
||
| 03/20/2025 | Commercial Mechanical Standard | REQUIRES RESUBMIT | Jorge Valido jvalido@safebuilt.com Denied Reason: Date Completed : 3/19/2025 4:19:57 PM 1. General - Provide COMcheck Mechanical Compliance Certificate. Any other APPROVED certifying agency is acceptable. - 2018 IECC Section C403.3.2 HVAC equipment performance requirements. 2. General - Provide Heat Load calculations. Show all O/A loads (cooling/heating) on Heat Load Calculations. Heat loads with O/A Ventilation rates and HVAC unit design may be substituted for COMcheck and Ventilation Calculations. - 2018 IECC Section C403.1.1 Calculation of heating and cooling loads |
||
| 03/20/2025 | Outdoor Lighting Standard | REQUIRES RESUBMIT | Electrical(E) Reviewer Ron Ross rross@safebuilt.com Denied Reason: Date Completed : 3/11/2025 5:55:01 PM 1. E1.0 LIGHTING NOTES AND DETAILS: Lighting Keynotes Hexagons are too dark and #s cannot be easily seen. Comment applies to lighting sheets too. This will affect the field drawings if sheets are printed out on smaller sheets at smaller scales. 2. E2.1 WEST POWER PLAN: drawing has some CAD artifacts just outside of the bathrooms that should be removed. 3. E2.2 EAST POWER PLAN: Should identify panels shown on E3.0 Electric Service Diagram. 4. E3.0 ELECTRICAL SCHEDULES: 208 Volt ATS is erroneously attached to 480 volt panel. Need to tie ATS into correct panel. If the intent is to provide back up to the entire facility, should select a 480 Volt generator and 480 Volt ATS. 5. E4.0 ELECTRICAL NOTES: Suggestion only, E4.0 should be an electrical cover sheet ie Sheet E0.0. |
||
| 03/07/2025 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 03/05/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |