Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL PDSD SIMPLE REVIEW v.4
Permit Number - TC-COM-0324-00451
Review Name: COMMERCIAL PDSD SIMPLE REVIEW v.4
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/17/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 06/17/2024 | Commercial Plumbing | REQUIRES RESUBMIT | A flowrate of 52 GPM will result in a water velocity of 8 feet per second, a 60-80 GPM demand will require the use of 2.5” PEX to limit the water velocity to 8 feet per second. Reference: Section 303.2, IPC 2018. [Third comment: Comment not addressed. Provide the water demand that the relocated 1-1/2” water meter will be serving.] [Second comment: A 1-1/2” water meter is allowed to serve a demand of up to 100 GPM which would result in an excessive water velocity for a 1-1/2” PEX water line. Provide the water demand that the relocated 1-1/2” water meter will be serving.] [Initial comment: Provide the water demand that the relocated 1-1/2” water meter will be serving. The submitted information states that the water service pipe will be 1” PEX. Reference Section 107.2.1, IBC 2018.] | ||
| 05/29/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |