Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - LIMITED v.1
Permit Number - TC-COM-0324-00425
Review Name: COMMERCIAL REVIEW - LIMITED v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/26/2024 | Commercial Electrical | APPROVED | |||
03/28/2024 | Site Zoning | APPROVED | |||
03/18/2024 | Site Engineering | NOT REQUIRED | |||
04/02/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
04/02/2024 | Commercial Building | REQUIRES RESUBMIT | Please submit your revised drawings along with a detailed response letter, which states how all Building Review Section comments were addressed. Sheet A1: Please amend and update the edition of the governing codes under General Notes to reflect the 2018 edition of the I-codes and the 2017 edition of the NEC. IBC 107.2.1 Additionally please include the 2018 IEBC. Sheet A1: Please amend plans to include a detailed description of the work involved in this permit’s scope. IBC 105.3 Based on available permitting history, these containers were Storage units #7&8. Sheet A1: Please provide the Soils Report #63155017 by Terracon Dated May 19, 2015, with the next submittal. IBC 107.2.1 Sheet A2: Please amend plans to indicate the following: IBC 107.2.1 Door size for new opening in larger container. Show door landing for above door. Indicate tempered glazing in window next to above door. Indicate the SHGC and the U-Factor for the new windows installed in the larger container. Sheet A2: Sheet A4: Please amend plans so all documents show the same information. Sheet A4 indicates a Type II hood and Sheet M2 depicts a Type I hood. Please resolve. IBC 107.2.1 Mark Masek Plans Examiner Mark.masek@tucsonaz.gov 520-837-4994 |
||
04/02/2024 | Commercial Mechanical | REQUIRES RESUBMIT | 1. Specify the type of venting system and the venting materials to be used for the proposed water heater. Reference: Section 503.1, IFGC 2018. 2. The Type II hood has 800 CFM of exhaust while the make-up air unit, MUA-1 provides 640 CFM. Show how adequate make-up air is to be provided to the room so that the room pressure remains essentially neutral. Reference: Section 501.4, IMC 2018. 3. Provide locking access port caps for the condensing unit per Section 1101.10, IMC 2018 or locate the condensing unit in a controlled |
||
04/02/2024 | Commercial Plumbing | REQUIRES RESUBMIT | Correct the description of equipment tag #16 as shown in the Low Pressure Propane Load chart. It is a gas-fired, double convection oven, not a “burner stove.” | ||
04/02/2024 | Water - PDSD | REQUIRES RESUBMIT | Show the location and size of the existing water meter, backflow preventer, and the water service pipe on a site plan. Reference: Section 107.2.1 and 107.2.6, IBC 2018. | ||
03/25/2024 | Fire New Construction | REVIEW COMPLETED | |||
03/14/2024 | PDSD Application Completeness | REVIEW COMPLETED |