Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0323-00918
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
05/01/2023 Commercial Electrical APPROVED
05/01/2023 Commercial Mechanical APPROVED
05/01/2023 Commercial Structural APPROVED
04/25/2023 Site Zoning APPROVED
04/19/2023 Site Engineering NOT REQUIRED
05/01/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
05/01/2023 Commercial Plumbing REQUIRES RESUBMIT Please correct the following:
1. Sections 701.4 and 1003.1, IPC 2018 amalgam waste. Dental offices to install either an ISO 11143:2008 amalgam separator or an ANSI/ADA Standard 108 amalgam separator. Non-contact amalgam waste are to be recycled.
2. Section 2902 IBC Required Minimum Plumbing Fixtures. Water Fountain is required and is mentioned in the cover sheet as provided. I don't see it on your drawing, please identify and label it on your drawing. If it does not exist, please install and show on your drawing.
3. Fire Sprinkler is required and processed as a separate permit. Submit the drawings to the Fire Department for review and approval. Electrical work related to installation of Emergency Lights, Lighted Signs, Audible Fire Alarm shall also be reviewed as part of the submittal. They will conduct inspection, their approval will be required prior to issuing Certificate of Occupancy.
3. Please re-submit.
04/21/2023 Fire New Construction REVIEW COMPLETED
04/05/2023 PDSD Application Completeness REVIEW COMPLETED