Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0323-00848
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/25/2023 | Commercial Structural | APPROVED | |||
| 04/03/2023 | Site Engineering | NOT REQUIRED | |||
| 04/25/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 04/17/2023 | Commercial Electrical | REQUIRES RESUBMIT | Please address the electrical plan review comments and provide a written response. 1 Revise the branch circuits assigned for devices and equipment that correlates with the panel schedule. Also note that some branch circuits are duplicated to various equipment. For example 2 The current adopted Electrical Code that applies to this project is the 2017 NEC not the IRC, see ‘General Electrical Notes’. Remove all references to the IRC and replace with the NEC. 3 Provide a detailed description of the scope of electrical work and identify what equipment or devices are existing to remain. 4 The Small Appliance branch circuits for the kitchen required by NEC art 210.11C, 210.52B shall be rated at 20 amps. 5 Provide compliance with the 2018 IECC for the lighting. Provide compliance with the City of Tucson Outdoor Lighting Code for the exterior lighting. Ref; 2018 IBC section 107.2.1, 2017 NEC, 2018 IECC, 2012 City of Tucson Outdoor Lighting Code. |
||
| 04/25/2023 | Commercial Mechanical | REQUIRES RESUBMIT | 1. Current Federal Regulations require residential split system heat pumps built after 01/01/2023 to have a minimum SEER of 15 (SEER2 = 14.3). 2. Coordinate the heating/cooling calculations with the specified split system heat pump. The calculations call for a greater cooling and heating capacity. In addition, the calculations and detail 2/M1.0 call for outside air to be supplied to the indoor unit .Reference: Section 107.2.1, IBC 2018. 3. Mechanical keynote #6 calls out a flue for the water heater. This is not needed for an electric water heater. |
||
| 04/25/2023 | Commercial Plumbing | REQUIRES RESUBMIT | Specify that all proposed plumbing fixtures shall be listed by a third-party certification agency as complying with the relevant standards. Reference: Section 303.4, IPC 2018. | ||
| 04/05/2023 | Site Zoning | REQUIRES RESUBMIT | |||
| 04/14/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 03/23/2023 | PDSD Application Completeness Express | REVIEW COMPLETED |