Review Status: Requires Resubmit

Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.2

Permit Number - TC-COM-0225-00404
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/06/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
11/06/2025 Air Balancing/Commissioning Report (Deferred Submittal) Express REQUIRES RESUBMIT The air balance report shows that the total air flowrate for AC-3 is still approximately 76% of the design value after two attempts to rectify the problem. Submit the air balance report to the engineer to determine a plan to resolve the impasse.
11/06/2025 PDSD Application Completeness Express REVIEW COMPLETED