Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: TC-COM-0225-00277
Parcel: 10911141D

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0225-00277
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
02/15/2025 Commercial Electrical Standard APPROVED Electrical(E) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 2/14/2025 1:15:19 PM
02/15/2025 Commercial Mechanical Standard APPROVED Mechanical(M) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 2/14/2025 2:40:55 PM
02/15/2025 Commercial Plumbing Standard APPROVED Plumbing(P) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 2/14/2025 2:41:05 PM
03/03/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
03/03/2025 Site Engineering Standard PENDING ASSIGNMENT
03/03/2025 Site Zoning Standard PENDING ASSIGNMENT
03/03/2025 Water - PDSD Standard PENDING ASSIGNMENT
02/15/2025 Commercial Building Standard REQUIRES RESUBMIT Structural(S) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 2/14/2025 11:47:49 AM



Building(B) Reviewer
Andrew Bevis
abevis@safebuilt.com
Denied
Reason:
Date Completed : 2/14/2025 11:27:03 AM
1. Sheet A-102/Occupant Load Calculation: The occupant load calculation provided is incorrect. It doesn't include the
waiting area. This area would be considered an assembly area and should be calculated accordingly. There is a
distinct difference between occupancy classification and occupancy use. The exceptions provided in Section 303.1.2
apply to that of classification and the requirements of max. allowable area, height, stories, mix-use requirements and
overall classification of the building. So yes, this room is considered as business in the overall context of the structure
and can comply with the business requirements previously mentioned. However, when calculating occupant loads,
one must calculate based on the use of the space. The waiting room's use is assembly, and the occupant load must
be calculated as such in accordance with Section 1004 and Table 1004.5. Provide a corrected occupant load in
accordance with 2018 IBC Table 1004.5.
2. General/Existing floor plans: No existing floor plan has been provided. Provide a detailed existing floor plan.
3. General/Demolition floor plans: No demolition floor plan has been provided. Provide a detailed demolition floor plan.
02/19/2025 Fire New Construction Standard REVIEW COMPLETED Fire Alarm modification will required a separate permit, adopted city codes are the 2024 IFC with local amendments.
02/11/2025 PDSD Application Completeness Express REVIEW COMPLETED