Permit Number: TC-COM-0225-00252
Parcel: 12801005H

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0225-00252
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
02/25/2025 Commercial Electrical Standard APPROVED Electrical(E) Reviewer
Janet Matz
jmatz@safebuilt.com
Approved
Reason:
Date Completed : 2/25/2025 3:14:12 AM
02/25/2025 Commercial Plumbing Standard APPROVED Plumbing(P) Reviewer
Janet Matz
jmatz@safebuilt.com
Approved
Reason:
Date Completed : 2/25/2025 3:13:53 AM
03/03/2025 Site Zoning Standard APPROVED
03/07/2025 Site Engineering Standard NOT REQUIRED
03/07/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
02/25/2025 Commercial Building Standard REQUIRES RESUBMIT Structural(S) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 2/25/2025 3:13:35 AM
1. Provide a letter stamped and sealed from a licensed engineer indicating that the existing roof structure is sufficient to support the new rooftop unit. It is unknown if the new unit is similar in size and weight as the existing.



Building(B) Reviewer
Janet Matz
jmatz@safebuilt.com
Approved
Reason:
Date Completed : 2/25/2025 3:14:34 AM
02/25/2025 Commercial Mechanical Standard REQUIRES RESUBMIT Mechanical(M) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 2/25/2025 3:14:57 AM
1. Provide a general layout for the main duct runs and verify if it is existing or new. It is unsure if the ductwork will be
replaced in the sales area since the reflected ceiling plan indicates the existing drywall ceiling is to remain in this area.
2018 IMC section 603.
2. Provide a detail showing how the new ductwork is to be attached from the existing ceiling structure. 2018 IMC section 603.10.
02/10/2025 Fire New Construction Standard REVIEW COMPLETED Fire alarm and fire sprinklers alterations requires a separate permit. Fire extinguishers shall be installed accordingly with the 2024 IFC Section 906
02/08/2025 PDSD Application Completeness Express REVIEW COMPLETED