Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0225-00215
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/19/2025 | Commercial Building Standard | APPROVED | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Approved Reason: Date Completed : 2/18/2025 5:31:38 PM Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Approved Reason: Date Completed : 2/7/2025 1:30:09 PM |
||
| 02/19/2025 | Commercial Electrical Standard | APPROVED | Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved with Comments Reason: Date Completed : 2/13/2025 5:33:11 PM |
||
| 02/19/2025 | Outdoor Lighting Standard | APPROVED | Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved with Comments Reason: Date Completed : 2/13/2025 5:33:11 PM |
||
| 03/05/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 02/19/2025 | Commercial Mechanical Standard | REQUIRES RESUBMIT | Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Denied Reason: Date Completed : 2/17/2025 9:48:58 AM 1. General - Provide Heat Load calculations - 2018 IECC Section C403.1.1 Calculation of heating and cooling loads. |
||
| 02/19/2025 | Commercial Plumbing Standard | REQUIRES RESUBMIT | Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 2/18/2025 11:12:52 PM First Plumbing Review: 1). Plan Page A1.3: Missing Lavatory Fixture spacing Measurements. Add Lavatory Fixture spacing Measurements.. -2018 IPC 405.3.1 2). Plan Page P1.1.1: Indirect waste piping that exceeds distances listed in -2018 IPC 802.3 shall be trapped. Update detail #2 to comply with -2018 IPC 802.3 3). Plan page P1.3 : Water piping to H201 (oven) needs backflow protection. Add Backflow protection device to H201 oven water connection -2018 IPC 608.3 4). Plan Page P1.2: Water riser missing the H201 oven water line. Add the H201 oven water line to the water riser. -2018 IPC 106.3.1 5). Plan Page P1.2 grease interceptor load table: The Floor sinks & floor drains can't have a DFU load of zero. Update the Grease interceptor load table with DFU amounts derived from -2018 IPC section 709 thru 709.4.1 |
||
| 03/05/2025 | Site Engineering Standard | REQUIRES RESUBMIT | TC-COM-0225-00215 5502 E GRANT RD Site Engineering approval for this permit cannot be granted until the associated development package (DP) -- TD-DEV-0924-00266 -- is issued. Although the DP is approved, outstanding pre-issuance conditions remain. Chris Arrington chris.arrington@tucsonaz.gov |
||
| 03/03/2025 | Site Zoning Standard | REQUIRES RESUBMIT | Although the plans appear to match, final Site Zoning approval for this permit cannot be granted until the associated development package (DP) -- TD-DEV-0924-00266 -- is issued. Although the DP has received all approval, outstanding pre-issuance conditions remain. Please reach out in case of any questions to fernando.garcia2@tucsonaz.gov. |
||
| 02/26/2025 | Water - PDSD Standard | REQUIRES RESUBMIT | Show the location and size of the proposed water meter, backflow preventer, and the water service pipe on a site plan. The development package is not a substitute for a complete site plan. Reference: Section 107.2.1 and 107.2.6, IBC 2018. | ||
| 02/14/2025 | Fire New Construction Standard | REVIEW COMPLETED | The CO2 system requires a separate operational permit per the 2024 IFC and local amendments. Install fire extinguishers as required per section 906, 2024 IFC. |
||
| 02/05/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |