Permit Review Detail
Review Status: Approved
Review Details: COMMERCIAL REVIEW - FULL v.3
Permit Number - TC-COM-0224-00342
Review Name: COMMERCIAL REVIEW - FULL v.3
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/20/2024 | Bldg Permits - Post Review Express | REVIEW COMPLETED | |||
| 05/17/2024 | External Reviewers - SAFEBuilt | REVIEW COMPLETED | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Approved with Comments Reason: Date Completed : 3/8/2024 12:04:43 PM 1. GENERAL - MECHANICAL LOADS: Dental Equipment Details on Sheets SED.1 thru SED.3 indicate that all new equipment shall be either slab-supported, counter- or wall-mounted. Dental Lights requiring ceiling reinforcement per Sheet SA.1 are understood to weigh less than 100 lb per Detail 6A on Sheet SED.1. No Mechanical Roof Plan has been provided. Therefore, it is the responsibility of the contractor and MEP designer to confirm that no new equipment in excess of 300 lb shall be supported from the roof or ceiling without the consultation of a structural engineer. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Approved Reason: Date Completed : 4/24/2024 10:43:49 AM Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Approved Reason: Date Completed : 3/11/2024 12:26:37 PM Electrical(E) Reviewer Andrew Bevis abevis@safebuilt.com Approved Reason: Date Completed : 5/10/2024 10:58:46 PM Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Approved Reason: Date Completed : 4/28/2024 6:49:18 PM Second Plumbing Review:OK Resolved-1). General: Building plan review comments 2 & 4 need to be addressed. -2018 IPC 106.3.1 2). The piping materials for sanitary, water, compressed air, med gas, & vacuum are missing from plan page P7, On plan page P7 please add a piping/fitting materials schedule according to -2018 IPC 605.4, 702, NFPA99 Resolved-3). The required med Gas room door sign verbiage is missing, add this information to plan page A4's door schedule according to -2018 NFPA99 5.1.3.1.9 |
||
| 05/13/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |