Permit Number: TC-COM-0224-00306
Parcel: 117150010

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0224-00306
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
03/25/2024 Water - PDSD APPROVED
03/20/2024 Signs NOT REQUIRED
03/12/2024 Site Engineering NOT REQUIRED
03/25/2024 Bldg Permits - Post Review PENDING ASSIGNMENT
03/20/2024 Design Review REQUIRES RESUBMIT This property is within the boundaries of the Rio Nuevo Area (RNA) overlay zone, and must comply with RNA standards. The Design Package with proposed modifications to the north and east facades was approved under Activity # T19SA00500 on January 14, 2020, and a modification to that approved Design Package was approved under Activity # SD-0423-00042 on May 22, 2023. The project for Starbucks is including modifications to the Design Packages just mentioned, which are available online here: https://pro.tucsonaz.gov/permitdetails/T19SA00500/ and here: https://pro.tucsonaz.gov/plandetails/SD-0423-00042/ . Please submit a revised Design Package reflecting the new proposal for the exterior of the Starbucks portion of the building, as a subrecord of TC-COM-0224-00306 via TDC Online, following these instructions: https://www.tucsonaz.gov/files/sharedassets/public/v/3/pdsd/documents/submission-documents/special_districts_application_instructions_7.18.23.pdf . Please send me an email to maria.gayosso@tucsonaz.gov if you have any questions. Thank you.
03/04/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Approved
Reason:
Date Completed : 2/28/2024 4:12:14 PM
No structural review required.



Building(B) Reviewer
Andrew Bevis
abevis@safebuilt.com
Denied
Reason:
Date Completed : 2/20/2024 2:32:45 PM
1. General: No information has been provided regarding the adjacent tenants above and beside tenant. This is a mix use situation. Provide clarification regarding the tenants and any necessary separations and allowable areas in relation to the overall structure in accordance with 2018 IBC Section 508.

2. General: Provide within the site plans, drawings that clearly indicate the accessible routes within the site and site arrival points that connect the accessible parking to the accessible entrances that are in accordance with 2010 ADAAG Section 206.2.1 and 206.2.2.

3. General: The service counter does not appear to be accessible as required. Provide a fully dimensioned section detail of the service counter in accordance with 2010 ADAAG and ICC/ANSI A117.1-2017 Sec. 904.3



Mechanical(M) Reviewer
Jorge Valido
jvalido@safebuilt.com
Denied
Reason:
Date Completed : 2/29/2024 2:26:03 PM
1. General - Provide roof plan Show clear dimensions of all equipment to edges of building. Provide clear dimensions of exhaust to O/A intakes - 2018 IBC Section [A]107.2.1 Information on construction documents. - 2018 IMC Section [BE] 304.11 Guards.

2. General - Provide ComCheck Mechanical compliance Certificate - 2015 IECC Section Section C103.2Information on construction documents.



Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Denied
Reason:
Date Completed : 2/29/2024 10:23:52 AM
Electrical Review of Starbucks
By: Ron Ross PE
E103 POWER PLAN DETAILS: Comment only, Keynote 9 comments concerning voltage requirements should not be needed. Panel/source voltage is 208V which is between 198-218 volts.

E601 ELECTRICAL SCHEDULES:

The Fault Current Notes declaration is unacceptable per Tucson city requirements.
Engineer shall derive estimated fault current from the local power company’s website that lists maximum fault current availability based upon the size of transformer feeding site power.

Then use this Maximum Fault rating at the location of Keynote 1 (on sheet E501). Next, calculate the short circuit value for Panel MP using the length of cable called out by Keynote 6. If Panel MP2 is next to MP1, it can use the same short circuit
value to determine both panels fully rated KAIC requirements.

If the engineer wishes to retain and use a 65/10 KAIC system, engineer shall call out the Main distribution board, main circuit breaker, feeder circuit breaker, and then specify Panels MP1 and MP2 that will maintain the 65/10 KAIC series rating required so that the reviewer can confirm 65/10 KAIC compliance.



Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Denied
Reason:
Date Completed : 3/2/2024 5:14:22 PM
First Plumbing Review:
1). notate the gas sizing table used on the gas load summary on plan page P101 -2018 IFGC 402.3

2). Fixture schedule on plan page P002 needs to include manufacturer names and model numbers or provide product spec manual- 2018 IPC 303

3). add watermain piping sizes periodically to riser on plan page to plan page P502 -2018 IPC 106.3.1, 604.1

4). Add Piping materials for water sanitary , gas to plan page P001 or provide spec manual -2018 IPC 605.4, 702, IFGC 403

5). Add combustion air illustration & method for the furnaces & water heater to the mechanical pages. -2018 IFGC 304, 503.1

6). Add the water heater exhaust illustrations & Method to mechanical pages -2018 -IFGC 503.1
03/19/2024 Historic REQUIRES RESUBMIT Property is a contributing resource to the Downtown National Register Historic District. Changes to the exterior require review and approval. Installation of the sign will require a separate permit. Please provide specifics on where and how the sign will be attached to the wall surface. The attachment should avoid any decorative features.
Staff is also concerned about the use of black opaque material on the historic windows. Consider using a white opaque material for the windows.
03/18/2024 Site Zoning REQUIRES RESUBMIT FROM: Nathan Herrera
PDSD Zoning Review Section

PROJECT: TC-COM-0723-01866
130 E CONGRESS ST Zoning C-1

TRANSMITTAL DATE:‎ March 18, 2024


COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

COMMENT: Zoning has reviewed the plans. As signage and external alterations are shown, Zoning cannot approve until the relevant reviewers for Historic, Signs, and Design Review have approved.

If you have any questions about this transmittal, Contact Nathan Herrera at Nathan.Herrera@tucsonaz.gov
03/13/2024 Fire New Construction REVIEW COMPLETED
02/16/2024 PDSD Application Completeness REVIEW COMPLETED