| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/27/2024 | Site Zoning | APPROVED | |||
| 03/18/2024 | Site Engineering | NOT REQUIRED | |||
| 03/28/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 03/25/2024 | Commercial Electrical | REQUIRES RESUBMIT | Please address the electrical plan review comments and provide a written response. 1 The branch circuits #'s and or feeders assigned to the mechanical units do not correlate with the panel schedules. NEC 408.4. Please clarify 2018 IBC section 107.2.1, 2017 NEC |
||
| 03/28/2024 | Commercial Mechanical | REQUIRES RESUBMIT | 1. Revise the design criteria (P1-M0.01) to show the elevation and temperature conditions for Tucson, Arizona, not Phoenix, Arizona. 2. Revise the General Notes (P1-M0.01) the display the codes applicable to the City of Tucson (e.g. not 2021 IMC, 2012 IMC, or ICC Electrical Code). 3. Clarify which of the three units (FC-OR, FC-SPD, and FC-PRE) should be labeled as fan coils or as blower coils. Reference: Section 107.2.1, IBC 2018. 4. Clarify the location of the humidifier. Sheets P1-M2.15, P1-M8.01, and P1-P2.12 show the unit at a remote location on the roof but detail 6/P1-M7.01 implies that the humidifier is located below the duct from FC-OR. Show how the steam condensate is drained and where the drain terminates. (Note that the manufacturer calls for the unit to be located where the ambient temperature is a maximum of 86 degrees Fahrenheit.) 5. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units. Reference: Section C403.1.1 and C403.3.1, IECC 2018. 6. Provide structural details to show how the fan coil units are to be connected to the building structure. Reference: Section 302.1, IMC 2018. 7. Show the size, routing, and termination of the condensate drain for the splitIU-1. Reference: Section 307.2.1, IMC 2018 as amended by the City of Tucson. 8. Provide calculations to verify that adequate ventilation will be provided for the spaces served by HP-4. Reference: Section 403.3.1.1, IMC 2018. 9. Provide calculations to verify that adequate ventilation will be provided for the spaces served by FC-OR, FC-SPD, and FC-PRE per ASHRAE Standard 170-2017. Reference: Section 407.1, IMC 2018. |
||
| 03/28/2024 | Commercial Plumbing | REQUIRES RESUBMIT | 1. Revise the design criteria (P1-P0.01) to show the latitude and elevation for Tucson, Arizona, not Phoenix, Arizona. 2. Provide a detail showing the plumbing connections to the humidifier. The detail shall include the valves, strainer, and water hammer arrestor, per the manufacturer’s installation instructions. Reference: Sections 303.2, 604.9, and 606.2, IPC 2018. 3. Provide backflow protection for the potable water connection to the humidifier. Reference: Section 608.17.10, IPC 2018. |
||
| 03/28/2024 | Commercial Structural | REQUIRES RESUBMIT | Please provide sheet A2.44E as referenced in Demo Plan call out. IBC 107.2.1 | ||
| 03/18/2024 | Fire New Construction | REVIEW COMPLETED | |||
| 02/27/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |