Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0124-00014
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/01/2024 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 01/22/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Denied Reason: Date Completed : 1/18/2024 11:01:13 PM 1. GENERAL - UPDATES: For project updates, please submit sheets with all changes clearly marked in revision clouds. Please provide a written response to each comment; updates without a clear response to all comments may not be reviewed. If you have any questions regarding the comments, you may contact me directly. Updates may result in additional comments. 2. GENERAL - FIRM REGISTRATION: The State of Arizona requires that all firms performing engineering services be registered with the Arizona State Board of Technical Registration (https://btr.az.gov/). At the request of the building official, the construction documents shall indicate the name and registration number of the engineering firm by which the signing engineer is employed. Please update the construction documents to comply with this provision. 3. GENERAL - GEOTECHNICAL REPORT: Please provide a copy of the site-specific geotechnical report referenced on Sheet S1.0. The report should support the appropriateness of the selected foundation system for the project site. All building code references must be updated to the current code adopted by the City. 4. S1.0 - DEFERRED SUBMITTALS: The list of deferred submittals provided in the structural general notes appears incomplete. Please update this list to indicate that design of the wood roof trusses is being deferred. Please be advised that we will place an Administrative Hold on the Certificate of Occupancy pending the submittal of all deferred structural drawings as a REVISION. All Revision fees will apply. 5. S2.0 - MISSING INFORMATION: Please provide a foundation wall ("FW") size where a callout is currently missing at the exterior wall of the Unisex Bathrooms. Refer to Architectural Floor Plan A2.3 for reference. 6. S4.0 - LAP LENGTH: Detail 9/S4.0 shows wall dowels between the continuous footing and foundation wall that appear to lack sufficient development length. Please verify the design intent and confirm the minimum length that the dowels must extend into the foundation wall. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Denied Reason: Date Completed : 1/15/2024 1:03:50 PM 1. General: No egress plans have been provided. Provide detail egress plans. 2. General: There is a reference to sheet A9.3, however, this sheet has not been provided. Provide the missing sheet for review. Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Approved Reason: Date Completed : 1/11/2024 12:06:18 PM Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved with Comments Reason: Date Completed : 1/12/2024 9:55:44 AM Electrical Review of Car Wash By: Ron Ross PE E2.1 CONDUIT PLAN: Could not locate Keynotes 10 and 14. E2.2 CARWASH EQUIPMENT CONNECTION PLAN: Could not locate Keynote 3. Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 1/21/2024 10:10:41 PM First Plumbing Review: 1). Add sidewall to fixture center measurements to plan page A7.2 -IPC 2018, 404.2, 405.3.1 2). Gas Piping Material not selected on plan page P5.0 -IFGC 2018, 403.1 3). Add Gas system legnth & sizing table used to gas load summary on plan page P5.1 -IFGC 402.3 4). Label the destination of each water line on plan page P4.3 to show the interior water piping system for the public & employee fixtures is protected from the car wash components. -IPC 2018 608.1, 608.3 5). Plumbing plans only show one roof drain/overflow plan page A4.0 shows 2? Plan pages need to correlate. -IPC 2018, 106.3.1 6). Toilets on plan page P3.0 are not vented properly-IPC 2018, 901.2.1, 912.1 7). add fixture branch sizes to plan page P3.0 -IPC 2018, 604.1 |
||
| 01/31/2024 | Site Engineering | REQUIRES RESUBMIT | See zoning comment | ||
| 01/09/2024 | Site Zoning | REQUIRES RESUBMIT | FROM: Paul Camarena PDSD Zoning Review Section PROJECT: TC-COM-0124-00014 4646 N ORACLE RD Zoning C-3 New car wash TRANSMITTAL DATE:‎January 9, 2024 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1.COMMENT: COMMENT: Zoning has reviewed the building plan for compliance with the unapproved TD-DEV-1223-00492, Zoning cannot approve the building plans until the DP is approved. COMMENT: Zoning will review the building plans on the next submittal as it relates to the zoning review purview and compare the building plan footprint, building height, and square footage and location to ensure consistency with the DP. If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
||
| 02/01/2024 | Water - PDSD | REQUIRES RESUBMIT | 1. Show the location and size of the proposed water meter, backflow preventer, and the water service pipe on a site plan. Typically, water meters are located at the property line, not within a building. Contact Tim Rowe at Tucson Water (tim.rowe@tucsonaz.gov) for assistance. The development package is not a substitute for a complete site plan. Reference: Section 107.2.1 and 107.2.6, IBC 2018. 2. Reduced pressure backflow prevention assemblies are required to be installed in locations accessible to Tucson Water. Reference: Chapter XXVII, Article V, Section 27-72, the Tucson Code, https://www.tucsonaz.gov/files/sharedassets/public/city-services/tucson-water/water-quality/documents/backflow-ordinance.pdf 3. Reduced pressure backflow prevention assemblies are required to be installed directly after the water meter for buildings that have chemicals, cleaning agents, or other contaminants that may come in direct contact with water. Reference: Chapter XXVII, Article V, Section 27-72, the Tucson Code, https://www.tucsonaz.gov/files/sharedassets/public/city-services/tucson-water/water-quality/documents/backflow-ordinance.pdf |
||
| 01/16/2024 | Fire New Construction | REVIEW COMPLETED | |||
| 01/05/2024 | PDSD Application Completeness Express | REVIEW COMPLETED |