Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-0123-00471
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/28/2023 | Site Zoning | APPROVED | |||
03/07/2023 | Site Engineering | NOT REQUIRED | |||
03/08/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
02/15/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: TC-COM-0123-00471 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Denied The proposed building location shown on the GIS views on pages T1.0 and SP1.0 do not match the location of the building shown on the site plan. Include a list of special or deferred inspections. BUILDING REVIEW COMMENTS: Denied The proposed building location shown on the GIS views on pages T1.0 and SP1.0 do not match the location of the building shown on the site plan. Show all emergency lighting (including the exit discharge lighting) on the electric and reflected ceiling plans. Page A1.4 references 2012 IBC in the accessibility notes - needs to be 2018 IBC. Need the COMcheck energy compliance for the interior lighting, exterior lighting, mechanical, or envelope as applicable. Include a list of special or deferred inspections. MECHANICAL REVIEW COMMENTS: Denied Need to include the existing and new mechanical equipment, exhaust fans, and ducts on reflected ceiling and MEP pages. Need the COMcheck energy compliance for the interior lighting, exterior lighting, mechanical, or envelope as applicable. ELECTRICAL REVIEW COMMENTS Denied Show all emergency lighting (including the exit discharge lighting) on the electric and reflected ceiling plans. Include the panel schedules for all new circuits and feeders. Need the COMcheck energy compliance for the interior lighting, exterior lighting, mechanical, or envelope as applicable. PLUMBING REVIEW COMMENTS: Denied Sprinklers are shown installed on some pages but not installed on the cover sheet. Need to show the new or replaced/repaired plumbing DWV, supply piping, water heater, fixtures, etc. If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
||
03/08/2023 | Fire New Construction | REQUIRES RESUBMIT | Sprinklers are shown installed on some pages but not installed on the cover sheet, please clarify. patricia.shelton@tucsonaz.gov 520.837.7082 |
||
02/08/2023 | PDSD Application Completeness | REVIEW COMPLETED |