Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/01/2023 | Site Engineering | APPROVED | |||
02/07/2023 | Site Zoning | APPROVED | |||
02/07/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
01/26/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: TC-COM-0123-00411 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: CONDITIONALLY APPROVED This approval is for the pool and spa only as noted in the scope of work on the drawings. All other work shall be indicated under a separate permit including but not limited to site engineering and drainage, required safety barriers (fencing), site work and utilities. BUILDING REVIEW COMMENTS: CONDITIONALLY APPROVED This approval is for the pool and spa only as noted in the scope of work on the drawings. All other work shall be indicated under a separate permit including but not limited to site engineering and drainage, required safety barriers (fencing), site work and utilities. MECHANICAL REVIEW COMMENTS: CONDITIONALLY APPROVED This approval is for the pool and spa only as noted in the scope of work on the drawings. All other work shall be indicated under a separate permit including but not limited to site engineering and drainage, required safety barriers (fencing), site work and utilities. ELECTRICAL REVIEW COMMENTS CONDITIONALLY APPROVED This approval is for the pool and spa only as noted in the scope of work on the drawings. All other work shall be indicated under a separate permit including but not limited to site engineering and drainage, required safety barriers (fencing), site work and utilities. PLUMBING REVIEW COMMENTS: DENIED PROVIDE HEATER GAS PIPING DETAILS AND SIZING CALCULATIONS. SHOW THE HEATER RELIEF PIPE DETAILS. SHOW THE EMERGENCY PUMP SHUT-OFF SWITCH DETAILS. If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
||
01/19/2023 | Fire New Construction | REVIEW COMPLETED | |||
01/17/2023 | PDSD Application Completeness | REVIEW COMPLETED |