Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Plan Number: T22PRE0233
Parcel: 11307046C

Review Status: Requires Resubmit

Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1

Plan Number - T22PRE0233
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
Fire New Construction REQUIRES RESUBMIT Building will require fire sprinklers
Site Engineering REVIEW COMPLETED 1. Ensure roof does not drain onto ADA sidewalk without scuppers/gutters
2. Ensure that restriped ADA spaces meet current requirements.
3. Insure that single container sufficient for refuse. Historically it appears that additional containers were utilized on the SW corner of the property.
4. N Campbell Ave is a Gateway Arterial and new development there is subject to special development guidelines (see Major Streets & Routes Plan page 22 https://www.tucsonaz.gov/files/pdsd/plans/MSR.pdf)
5. Maximize water harvesting in any new landscaping.

Faffs Riederer
faffs.riederer@tucsonaz.gov
Site Landscape REVIEW COMPLETED 1. Any and all landscape improvements will need a landscape plan and irrigation plan submitted.
2. Maximize and all all water harvesting into new landscaped areas.
Site Zoning REVIEW COMPLETED CDRC Thursday Pre-Submittal Transmittal
PDSD Zoning Review
FROM: Paul Camarena, Planner
PROJECT: Thursday Pre-submittal meeting –
Address: 2943 N CAMPBELL AV
Parcel(s): 11307046C
Zoning: C-1
Existing Use: Food service
Proposed Use: Food service
TRANSMITTAL DATE: 10/25/2022

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 - Development Package.
2. The use is Food Service: Excluding Soup Kitchens, which is permitted in the C-1 zone. The development is subject to use specific standards C-1: 4.9.4.M.1 & 5 and 4.9.13.O
3. Vehicular parking requirements are 1 space per 100 sq. ft. GFA, 50 spaces are required with 3 being an accessible parking space
4. Bicycle Parking - Short-term parking 1 space per 2,000 sq. ft. GFA, the minimum requirement is 2 spaces, Long-term parking 1 space per 12,000 sq. ft. GFA, the minimum requirement is 2 spaces;
5. The minimum width of a two-way PAAL is 24 ft.
6. Ensure access standards found in section 7.8 of the UDC and sections 7-01.0.0 and 10-01.0.0 of the Technical Standards Manual are met. Pedestrian access along the street is required. Show complete pedestrian circulation for the site.
7. Bicycle parking requirements- See 7.4.9.2.
8. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.
If you have any questions, please contact me at Paul.Camarena@tucsonaz.gov
Traffic Engineering Review REVIEW COMPLETED
TW Hydraulic Modeling Review REVIEW COMPLETED 1. Tucson Water’s New Area Development Unit has no objections to the proposed development.
2. The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to:

Tim Rowe, P.E., Civil Engineer
Tucson Water, New Development Section
201 N. Stone Avenue, #2-220
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106
tim.rowe@tucsonaz.gov