Permit Number: T22CM08145
Parcel: 13824101L

Review Status: Requires Resubmit

Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1

Permit Number - T22CM08145
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
06/26/2023 Bldg Permits - Post Review Express PENDING ASSIGNMENT
06/26/2023 Air Balancing/Commissioning Report (Deferred Submittal) Express REQUIRES RESUBMIT The air balance report shows that EF-2 is not able to achieve more than 66% of the design exhaust flow rate. The engineer of record shall review the situation and determine the course of action prior to the air balance report being resubmitted. Reference: Section 403.3.1.5, IMC 2018.