Permit Review Detail
Review Status: Requires Resubmit
Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Permit Number - T22CM08145
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/26/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 06/26/2023 | Air Balancing/Commissioning Report (Deferred Submittal) Express | REQUIRES RESUBMIT | The air balance report shows that EF-2 is not able to achieve more than 66% of the design exhaust flow rate. The engineer of record shall review the situation and determine the course of action prior to the air balance report being resubmitted. Reference: Section 403.3.1.5, IMC 2018. |