Permit Number: T22CM07950
Parcel: 11504520B

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.3

Permit Number - T22CM07950
Review Name: COMMERCIAL REVIEW - FULL v.3
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
06/12/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
05/30/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Activity Number: T22CM07950

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.

Structural(S) Reviewer
Daljit Benipal
dbenipal@safebuilt.com
Conditionally Approved
Reason:
Date Completed : 10/31/2022 2:26:07 PM
NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances.

Structural(S) Reviewer (from previous submittal TUC8605001.101822)
Daljit Benipal
dbenipal@safebuilt.com
Conditionally Approved
Reason:
Date Completed : 10/31/2022 2:26:07 PM
NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances.

Mechanical(M) Reviewer
Neil Samaan
nsamaan@safebuilt.com
Denied
Reason:
Date Completed : 5/26/2023 8:07:01 PM
1. Show how you are bringing fresh outside ventilation air to the 6 FCU sheet M2.01 (IMC2018,106.3.1) Complied
2. Provide ventilation calculations (IMC2018,403.3.1.1.1) 1. Zone 2 requires 1290 cfm of outside air and it is being ventilated by FC-2 which is capable of 1150 total cfm's you can only bring in 20% outside air to the total capacity the numbers are way off please correct. 2. storage areas require ventilation at .06 cfm per square foot please correct. Not Complied
3. Your plans shall be made clear in the mail, study area, it is cluttered and not clear sheet M2.01 (IMC2018,106.3.1) Complie

Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Approved
Reason:
Date Completed : 5/9/2023 6:44:40 PM


Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Conditionally Approved
Reason:
Date Completed : 5/29/2023 3:06:01 PM
Third Plumbing Review: OK Subject to field inspections
1). OK
2). Coffee water connection will need an ASSE 1024 Backflow -IPC 608.17.1.2 ,Subject to field inspections
3). OK
4). Ok
5). SK-1 sink selection not detailed, will need to meet IPC section 303, Subject to field inspections
06/12/2023 Fire New Construction REVIEW COMPLETED
05/24/2023 PDSD Application Completeness REVIEW COMPLETED