Review Status: Requires Resubmit
Review Details: RESIDENTIAL SIMPLE REVIEW v.1
Permit Number - T22CM05537
Review Name: RESIDENTIAL SIMPLE REVIEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/21/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 06/20/2023 | Residential Building | REQUIRES RESUBMIT | T22CM05537 PLAN REVIEW COMMENTS Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. For facilitating a shorter back check time, please provide an updated complete plan set with a written response to each of the notated items indicating action taken. Do not cloud the changes made for comment revisions. SCOPE OF REVIEW: The scope of this plan review covers architectural, plumbing, mechanical, energy conservation and electrical. All code references are to the 2018 International Residential Code and 2018 International Energy Conservation Code. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet Zoning and other departmental requirements, conditions, and concerns before permit approval. SITE PLAN: 1. Show the size of electric service and conductor rating to each building, R106.1.1. Identify the utility lines requiring upgrade or replacement since the last approved (with final inspection) permit. This information should be shown on a riser diagram. FLOOR PLANS: 1. Provide a layout of all utility devices and appliances in the Utility Room including appropriate electrical outlets and panel schedule, R106.1.1. Identify all alterations and improvements as part of this permit or restore as an unimproved storage shed. ELECTRICAL PLANS: 1. Smoke alarms are required outside each separate sleeping area, R314.3.2. Show a smoke alarm in each bedroom and outside in the immediate vicinity for Unit #2. 2. Provide an electrical riser diagram for each service, E3403. Identify the Utility Room sub panel with feeder protection. 3. Provide a panel schedule showing panel size, circuit numbers, ampacity, wire size and general description for Unit #2 and the Utility Room, E3404.13 & E3706.2. Provide clear labeling of information and location markers for all electrical Panels and sub-Panels. Provide separate panel schedules for Units 1 and 2. Provide separate “elect Boxes” schedules, and label what structure the “elect Boxes” support. 4. Show two or more 2O AMP small appliance circuits at the kitchen countertop receptacle outlets; they may also serve the breakfast room and dining room, but not other locations, E3703.2 and E3901.3. Remove the bathroom from the kitchen countertop circuit in Unit #2. Show Bathroom receptacles with a separate 20 AMP dedicated circuit, E3703.4 and E3901.6. 5. Protect extended branch circuits with combination type arc-fault circuit interrupters, or an AFCI type receptacle at the first outlet on the branch circuit, E3902.17. 6. Show at least one wall switch controlled light at outdoor entrances or exits, E3903.3. Include the Utility Room exits. 7. Clarify which Unit# the Shed is attached to. Show the electrical box/sub-panel in the main Panel Schedule. If you have any questions, please contact: Jeremy Hamblin by email-Jeremy.Hamblin@tucsonaz.gov City of Tucson Residential Plan Review |
||
| 06/21/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: Paul Camarena PDSD Zoning Review Section PROJECT: T22CM05536 - T22CM05537 Electrical 3131 N CASTRO AV Zoning O-3 TRANSMITTAL DATE: June 21, 2023 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1.COMMENT: Please see residential comment. Additional comment may be forth coming. If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
||
| 06/15/2023 | PDSD Application Completeness Express | REVIEW COMPLETED | |||
| 06/15/2023 | Site Engineering | REVIEW COMPLETED | |||
| 06/15/2023 | Site Landscape | REVIEW COMPLETED |