Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
12/28/2022 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
12/15/2022 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: T22CM05106/BLDG #1 T22CM05107/BLDG #2 T22CM05108/BLDG #3 T22CM05109/BLDG #4 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: APPROVED BUILDING REVIEW COMMENTS: APPROVED MECHANICAL REVIEW COMMENTS: CONDITIONALLY APPROVED 1. Provide make up air for laundry room in an approved manner, if the HVAC unit is providing make up air then it shall be interlocked to the dryers and noted as such sheet M101 (IMC2018,504.6) Complied 2. All HVAC unit's shall be labeled on the mechanical HVAC Plan (e.g. AC-1, AC-2 etc.). sheet M101 (IMC2018,106.3.1) Complied 3. Exhaust method ventilation shall operate continuous at all times. you are not clear when you say that there is an on/off switch for the bathroom exhaust fans, that you are using for ventilation of the units on note 5, tenants shall not have the option of turning the ventilation off. sheet M201 (IMC2018,405.1) Complied ELECTRICAL REVIEW COMMENTS: APPROVED PLUMBING REVIEW COMMENTS: DENIED Second Plumbing Review: 1 thru 3 OK 4). SAME-Community Bldg. kitchen sinks need to discharge thru grease interceptor. -IPC 1003.1 ** Comment response states approval letter from utility authority was attached?** 5 thru 7 OK If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
||
12/12/2022 | Fire New Construction | REQUIRES RESUBMIT | no files attached | ||
12/02/2022 | Site Engineering | REQUIRES RESUBMIT | The associated development package must be approved before any combination permits can be approved. Please include relevant plans and documents. Lianne Evans lianne.evans@tucsonaz.gov |
||
11/16/2022 | Site Zoning | REQUIRES RESUBMIT | FROM: Paul Camarena PDSD Zoning Review Section PROJECT: T22CM05106, T22CM05107, T22CM05108, T22CM05109 Multi Family (2nd review) 6226 E LEE ST Zoning R-3 TRANSMITTAL DATE: November 16, 2022 Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. Comment: Zoning has reviewed the building plans for compliance with the associated Development Package DP22-0145 Zoning cannot approve the building plans until the DP is approved. If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov |
||
11/10/2022 | Commercial Plumbing | REVIEW COMPLETED | |||
12/28/2022 | Fire New Construction | REVIEW COMPLETED | |||
11/10/2022 | PDSD Application Completeness | REVIEW COMPLETED |