Permit Number: T22CM05106
Parcel: 121080610

Review Status: Requires Resubmit

Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1

Permit Number - T22CM05106
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
12/13/2024 Masonry Inspection (Deferred Submittal) Express APPROVED
12/13/2024 Site Prep Inspection (Deferred Submittal) Express APPROVED
12/17/2024 Bldg Permits - Post Review Express PENDING ASSIGNMENT
12/12/2024 Air Balancing/Commissioning Report (Deferred Submittal) Express REQUIRES RESUBMIT The air balance report shows that EF-55 is specified to exhaust 100 CFM but is actually exhausting 55 CFM. Submit the report to the mechanical engineer for resolution prior to resubmitting the air balance report. Reference: Section 403.3.1.5, IMC 2018.
12/17/2024 Concrete Installation Inspection (Deferred Submittal) Express REVIEW COMPLETED
12/17/2024 Other Inspection Reports (Deferred Submittal) Express REVIEW COMPLETED REINFORCING STEEL
12/12/2024 PDSD Application Completeness Express REVIEW COMPLETED
12/17/2024 Post-Installed Anchor Inspection (Deferred Submittal) Express REVIEW COMPLETED
12/17/2024 Post-Tension Inspection (Deferred Submittal) Express REVIEW COMPLETED