Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - T21CM07679
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/31/2022 | Commercial Electrical | APPROVED | Please address the following electrical plan review comments and provide a written response. Ref; Outdoor Lighting Calculations. Outdoor Lighting Code. Provide full compliance as outlined per section 104. 1. Provide a complete inventory of all the exterior lighting on this parcel and include it in the exterior lighting calculations, including the Picnic Ramada, Pool area, Breezeway, Building exterior, or any other existing lighting on the property, per section 104.2, 104.2.1. 2. Indicate the size of the parcel in acres. And use the correct lighting area option in table 401.1. Be advised, the 55,000 limit per acre is for residential zoned property. Should be using option 1,2,or 3 whichever applies. 3. Indicate on the plans if a special inspection is required for the Outdoor Lighting. Per section 104.2.2, 106.2.1 4. Unless provided by the pool/spa plans and permit documents. Provide a complete grounding detail for the pool/spa and equipment, also GFI protection for pumps and lighting as required per NEC art 680. 5. Provide compliance with the 2018 IECC for the lighting energy limits. Ref; 2018 IBC section 107.1, 2017 NEC, 2018 IECC ,City of Tucson Commercial Plan Submittal Requirements, Tucson/Pima County Outdoor Lighting Code (OLC). |
||
10/31/2022 | Commercial Mechanical | APPROVED | 1. Demonstrate energy code compliance for the building envelope using calculations based on the current code (e.g. COMcheck). Reference: Sections C101.5, C103.2, C303, and C401.2, International Energy Conservation Code 2018. 2. Specify the required maximum U-factors and Solar Heat Gain Coefficients (SHGC) for the fenestration and doors on the architectural drawings. Reference: Section C103.2, IECC 2018 3. Show that the proposed HVAC system meets the requirements of Sections C403.2, C403.3.2 (e.g. provide the mechanical energy code compliance certification from COMcheck). Reference: Section C303.1, International Energy Conservation Code 2018 4. Full compliance with the 2018 IECC for new buildings requires that an "additional efficiency package option" be selected per Section C406. Identify which of the eight options has been selected. Reference: Section C401.2 (2), IECC 2018. 5. Provide heating and cooling load calculations to justify the heating/cooling capacities of the specified HVAC units. Reference: Section C403.1.1 and C403.3.1, IECC 2018. 6. Verify that the installer setup menu for the specified programmable thermostat includes off-hour and set-back control, automatic shutdown and automatic start-up control (i.e. the thermostat is capable of automatically adjusting the start time of the HVAC equipment in order to bring the interior conditions to the desired temperature at the start of occupancy) and, if the thermostat does not require manual changeover from the heating and cooling modes, it restricts set point overlap. Reference: Section C403.4.2.3, IECC 2018. 7. Verify the model number of the specified condensing unit. Reference: Section 107.2.1, IBC 2018. |
||
10/31/2022 | Commercial Structural | APPROVED | |||
10/31/2022 | Fire New Construction | APPROVED | |||
10/31/2022 | Site Zoning | APPROVED | ZONING REVIEW TRANSMITTAL FROM: PDSD Zoning Review PROJECT: T21CM07679 6800 E Camino Agua Limpia. – PAD-7 La Estancia – Phase II Pool Amenity (1st Review) TRANSMITTAL: October 13, 2021 This site is located in the PAD-7 the proposed is an allowed use. 1. The proposed site/landscape pool/park development needs to be submitted as a Development Package (DP). This DP shall meet the requirements of Administrative Manual 2-06. Zoning will not be able to approve the building plans until a DP is submitted and approved. 2. Provide a copy of the required approval letter from the La Estancia Design Review Committee with the required DP and your next submittal of the building plans. If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov. |
||
11/01/2022 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
11/01/2022 | Commercial Plumbing | REQUIRES RESUBMIT | The maximum distance between cleanouts shall be 100-feet, measured along the developed pipe length from the upstream entrance of the cleanout. The section of the building sewer between the second and third cleanouts appears to have a developed length in excess of 108 feet. Reference: Section 708.1.1, IPC 2018. [Second comment: Comment not resolved; the site plan is, “for reference only” and no civil plans have been provided to show that the building sewer is code compliant (e.g. cleanouts).] [Initial comment: Provide a site drawing showing the size, route, and slope of the building sewer and the location of its connection to the public sewer. Reference: Section 107.2.1, IBC 2018.] |