Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: DP22-0226
Parcel: 11707297A

Address:
275 E 18TH ST

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE REVIEW v.1

Permit Number - DP22-0226
Review Name: DEVELOPMENT PACKAGE REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/10/2022 CDRC Post Review PENDING ASSIGNMENT
10/27/2022 Commercial Plumbing REQUIRES RESUBMIT The rim elevation of the next upstream sanitary manhole (9891-04, 2411.46') is more than 12"below the first floor elevation of building 1 (2413.50') and building 2 (2412.85'). Backwater valves shall not be installed per Section 714.1, IPC 2018, as amended by the City of Tucson.
10/27/2022 External Reviewers - Tucson Airport Authority REQUIRES RESUBMIT Changes requested.
View letter in DOCUMENTS section of PRO - "TAA review comments, first submittal, 09.01.22".
10/27/2022 External Reviewers - Tucson Electric Power (TEP) REQUIRES RESUBMIT email from: TEP-DEVREV <TEPDEVREV@tep.com>
Sent: Wednesday, September 21, 2022 8:20 AM
To: CDRC <CDRC@tucsonaz.gov>
Subject: Shiner Armory Park, S22-054

TEP has reviewed plans received on September 12th, 2022, the plat for the Shiner Armory Park, Lots 1 through 6 subdivision. Please note that TEP is awaiting customer approval of the Preliminary Construction Design.

Customer approval and a copy of the Approved Tentative Plat are required for TEP to prepare a final Construction Drawing. If revisions to the preliminary design are needed, easements are required for TEP facilities if not appropriately recorded on the final subdivision plat. They will need to be obtained by a separate instrument.

Costs for removing or relocating existing TEP facilities will be billable to the developer. The customer is responsible for compliance with City Ordinances. Please note a jurisdictional permit for any work on a public road right of way where applicable.

Tucson Electric Power Co.
Land Resources Department,
attn: Diane
11/07/2022 Historic REQUIRES RESUBMIT Property is located within the Armory Park Historic Preservation Zone and as such must be reviewed by the Armory Park Historic Zone Advisory Board and the Tucson Pima County Historical Commission Plans Review Subcommittee. Please complete the Historic/Special Districts application.
10/27/2022 Site Engineering REQUIRES RESUBMIT 1. Provide written approval from DTM (David Marhefka) for landscaping/water harvesting in the right-of-way.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
10/27/2022 Site Landscape REQUIRES RESUBMIT Landscape/irrigation plan required per UDC 8.7.3.H.
10/27/2022 Site Zoning REQUIRES RESUBMIT PROJECT: Shiner Armory Park Lots 1-6
Development Package (1st Review)
DP21-0226

TRANSMITTAL DATE: August 24, 2022

COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is August 10, 2023.

CONTENT REQUIREMENTS

1. COMMENT: 2-06.4.3 – Provide the development package case number, DP21-0226, adjacent to the title block on all sheets.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A.8 - For development package documents provide:

2. COMMENT: 2-06.4.7.A.8.a – Clarify what the accessory building is that is shown on lot 1.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

3. COMMENT: 2-06.4.9.H.5.a – Based on discussions with staff it has been determined that the vehicle parking calculation is no correct. Lots 4, 5 & 6 do not front on a street with parking on both sides, UDC Article 7.4.6.B.2.b, therefore the calculation needs to be revised to show that 3 visitor spaces are required for Lots 4, 5, & 6 and Lots 1, 2 & 3 require 1 visitor space.

4. COMMENT: 2-06.4.9.O – The required north perimeter yard setback to the north project boundary, based on a wall height of 16.25’, should be 10.83’.

5. COMMENT: 2-06.4.9.O – The required street perimeter yard setback to 4th Ave, based on a wall height of 24.16’, should be 24.16’ as measured to the back of curb.

6. COMMENT: 2-06.4.9.O – The required east perimeter yard setback to the east project boundary, based on a wall height of 16.25’, should be 10’-10”.

7. COMMENT: 2-06.4.9.O – The required street perimeter yard setback to 18th St, based on a wall height of 24.16’, should be 24.16’ as measured to the back of curb.

8. COMMENT: 2-06.4.9.O – The required street perimeter yard setback to 18th St, based on a wall height of 16.25’, should be 21.00’ as measured to the back of curb.

9. COMMENT: 2-06.4.9.O – The required street perimeter yard setback to Herbert Ave, based on a wall height of 16.25’ should be 8.125’ as measured to the back of curb.

10. COMMENT: 2-06.4.9.O – List the setback requirements for interior lots on the plan, see 8.7.3.L


If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov.

To resubmit your plans for additional review, please visit: https://docs.tucsonaz.gov/Forms/tucsonpermitapp

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
10/27/2022 Traffic Engineering Review REQUIRES RESUBMIT DP22-0226
Comments:

(Pg. 4- Site Plan)
1. Any existing curb, sidewalk and curb access ramps which are not compliant with current standards will be modified or replaced to meet current standards.
2. New Concrete Curb shall be per P.A.G. standard 209.
3. Concrete sidewalk per P.A.G. standard 200. New sidewalk is to be 5 Ft. wide.
4. Connect new sidewalk to existing per P.A.G. standard 203. (Taper from 4 Ft wide to 5 Ft. wide.)
5. Concrete curb access ramp per P.A.G. standard 207.
6. Existing curb may remain if it is compliant with current standards.
7. Existing sidewalk may remain if it is compliant with current standards.
8. New Driveway Apron's per P.A.G. standard 206. (Keynote No. 20, shall be standard 206 driveway aprons.)

David Stiffey
DTM Project Coordinator
David.Stiffey@tucsonaz.gov
11/10/2022 Design Review REVIEW COMPLETED FLD Design Review not Required