Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: DP22-0074
Parcel: 140360170

Address:
4975 E BENSON HY

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE REVIEW v.1

Permit Number - DP22-0074
Review Name: DEVELOPMENT PACKAGE REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/18/2022 Fire New Construction APPROVED
11/18/2022 Site Landscape APPROVED
02/06/2023 CDRC Post Review PENDING ASSIGNMENT
10/28/2022 Commercial Plumbing REQUIRES RESUBMIT Change One section of the building sewer shows a horizontal distance of 100.00 feet. With a distance of 8.75 feet from the upstream cleanout rim and the invert of the sewer section, the total developed length is 108.75 feet. Reduce the distance between cleanouts per Section 708.1.1, IPC 2018. [Initial comment: The maximum distance between cleanouts for the building sewer shall be 100-feet, measured along the developed pipe length from the upstream entrance of the cleanout. Reference: Section 708.1.1, IPC 2018.]
10/28/2022 Site Engineering REQUIRES RESUBMIT 1. See previous comment 2 - The trash enclosure detail needs to match section 8 of the Technical Standards Manual or a TSMR (Technical Standards Modification Request) will be needed and approved by Environmental Services. The minimum standards found in Section 8 of the TSM have not been met and the detail for the construction of the trash enclosure needs to be included in the Development Package since it is inspected by the site inspectors not the building inspectors.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
10/28/2022 Site Zoning REQUIRES RESUBMIT FROM: PDSD Zoning Review

PROJECT: QuickTrip No. 1499
Development Package (2nd Review)
DP22-0074

TRANSMITTAL October 17, 2022

DUE DATE: October 14, 2022

COMMENT: Resubmit revised drawings and a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is May 10, 2023.

CONTENT REQUIREMENTS

1. The DP case number should be DP22-0074 not “DPP22-0074”. COMMENT: 2-06.4.3 – Provide the development package case number, DP22-0074, adjacent to the title block on all sheets.

2. This comment was not fully addressed, show the entire PAD on the plan. COMMENT: 2-06.4.6 – Provide a reduced-scale map of the PAD on the first sheet, indicating the location of the portion being developed.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

3. Until the required documentation is provided Zoning cannot approve the DP. COMMENT: 2-06.4.7.A.6.a – Per PAD-21 Section III.N provide approved documentation that the required design review has been completed.

2-06.4.8 - Existing Site Conditions
The following information shall be provided on the plan/plat drawing to indicate the existing conditions on site and within 50 feet of the site. On sites bounded by a street with a width of 50 feet or greater, the existing conditions across the street will be provided.

4. Show the easement on the plan as to be abandoned per separate instruments. COMMENT: 2-06.4.8.B – There is an existing 10' SLOPE EASEMENT SEQ 20122220449 that runs along Valencia Rd that is not shown on the plan.

5. This comment was not addressed. COMMENT: 2-06.4.8.C – Dimension the location of the curbs & sidewalks and provide the sidewalk width for both streets.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

6. Until the dedication is complete Zoning cannot approve the DP. COMMENT: 2-06.4.9.I – The proposed right-of-way dedication called out on the plan will need to be completed prior to approval of this DP.

7. Until the information is provided Zoning cannot approve the DP. COMMENT: 2-06.4.9.L - There are numerous proposed easements shown on the plan that do not match what is shown on final plat S22-032. Once the final plat is recorded provided the recordation information for all easements shown :PER FINAL PLAT”.

If you have any questions about this transmittal, please contact Nicholas Ross at Nicholas.Ross@tucsonaz.gov.

To resubmit your plans for additional review, please visit: https://docs.tucsonaz.gov/Forms/tucsonpermitapp

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
10/28/2022 Traffic Engineering Review REQUIRES RESUBMIT DP22-0074
Comments:
1. A PIA is going to be required for this project. https://www.tucsonaz.gov/tdot/private-improvement-agreement Contact TDOT Engineering for information. DOT-Engineering-Review-Section@tucsonaz.gov Or call. 520-791-5100 Jesus Villezcas

David Stiffey
DTM Project Coordinator
David.Stiffey@tucsonaz.gov
12/01/2022 External Reviewers - Pima County Addressing REVIEW COMPLETED Good morning,
Please remove Pima County Addressing from the review for this project. The appropriate address for
the DP is 5115 E Valencia RD.
Thank you
Nicholas Jordan
Site Review Project Manager - Addressing Official
Pima County Development Services Department
201 N Stone AV – 1st Floor
Tucson, AZ 85701
(520) 724-9623