Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE REVIEW v.1
Permit Number - DP22-0053
Review Name: DEVELOPMENT PACKAGE REVIEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/20/2023 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 06/20/2023 | CDRC Review Coordinator Express | PENDING ASSIGNMENT | |||
| 06/20/2023 | Commercial Plumbing | PENDING ASSIGNMENT | |||
| 06/20/2023 | Fire New Construction | PENDING ASSIGNMENT | |||
| 06/20/2023 | NPPO | PENDING ASSIGNMENT | |||
| 06/20/2023 | ROW Engineering Review | PENDING ASSIGNMENT | |||
| 06/20/2023 | Site Engineering | PENDING ASSIGNMENT | |||
| 06/20/2023 | Site Landscape | PENDING ASSIGNMENT | |||
| 06/20/2023 | Site Zoning | PENDING ASSIGNMENT | |||
| 06/20/2023 | OK to Submit - Zoning Fast | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: Super Star Car Wash – 5225 E. Speedway Blvd. DP22-0053 Development Package – Revision #1 (OK to Submit) TRANSMITTAL DATE: June 20, 2023 The development package has been reviewed by the Zoning Review Section for minimal compliance with the Administrative Manual Section 2-06. 1. Provide the stamped and approved plan set including only sheets that are being revised with the area being changed clouded with a revision delta. The revision letter shall clearly state what sheets are being revised. If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov. |
||
| 06/15/2023 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 06/15/2023 | OK to Submit - Engineering Fast | REVIEW COMPLETED | |||
| 06/16/2023 | OK to Submit - Landscape Fast | REVIEW COMPLETED |