Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE REVIEW v.2
Permit Number - DP20-0173
Review Name: DEVELOPMENT PACKAGE REVIEW v.2
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/29/2023 | Commercial Plumbing | APPROVED | |||
03/17/2023 | NPPO | APPROVED | |||
03/27/2023 | Site Engineering | APPROVED | |||
03/17/2023 | Site Landscape | APPROVED | |||
04/03/2023 | CDRC Post Review | PENDING ASSIGNMENT | |||
03/23/2023 | Site Zoning | REQUIRES RESUBMIT | CDRC TRANSMITTAL PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: TAC2 – New Shell Building Development Package (1st Review - Revision #2) DP20-0173 TRANSMITTAL DATE: March 23, 2023 DUE DATE: April 05, 2023 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 2-06.3.0 FORMAT REQUIREMENTS 1. COMMENT: 2-06.3.12 – The drawing index on sheet 1 should not change from the last approved plan unless you are adding or removing addition sheets. Sheet A1.1 is a building plan sheet and will not be reviewed with the DP, remove this sheet from the set. If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
||
03/15/2023 | CDRC Review Coordinator | REVIEW COMPLETED | NO EXTERNAL REVIEWERS ADDED OR NEEDED | ||
03/28/2023 | Fire New Construction | REVIEW COMPLETED | |||
04/03/2023 | ROW Engineering Review | REVIEW COMPLETED | DP20-0173 6818 S. Country Club Rd. Comments: 1. A PIA is going to be required for this project. https://www.tucsonaz.gov/tdot/private-improvement-agreement Contact TDOT Engineering for information. DOT-Engineering-Review-Section@tucsonaz.gov Or call. 520-791-5100 Jesus Villezcas 2. A PIA Number must be provided prior to DP approval. David Stiffey DTM Project Coordinator David.Stiffey@tucsonaz.gov |