Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE NEW v.1
Permit Number - DP18-0081
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/18/2024 | Commercial Plumbing | APPROVED | |||
04/30/2024 | NPPO | APPROVED | |||
04/30/2024 | Site Landscape | APPROVED | |||
04/17/2024 | Site Zoning | APPROVED | |||
04/30/2024 | CDRC Post Review | PENDING ASSIGNMENT | |||
04/18/2024 | Site Engineering | REQUIRES RESUBMIT | The Design Standards for Stormwater Detention and Retention manual can be found online at https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/engineering-code/updated-retention-detention-manual.pdf 1. The the basin has 3:1 slope and the height of the slope is greater than 2 feet. Per DSSDR Chapter 4.11.1 a security barrier is required anywhere where the height of the slope is greater than 2 feet. Lianne Evans lianne.evans@tucsonaz.gov |
||
04/03/2024 | CDRC Application Completeness | REVIEW COMPLETED | |||
04/10/2024 | CDRC Review Coordinator | REVIEW COMPLETED | External Reviewers not required. No further action is required from the customer at this time. | ||
04/14/2024 | Fire New Construction | REVIEW COMPLETED | |||
04/09/2024 | OK to Submit - Engineering | REVIEW COMPLETED | |||
04/09/2024 | OK to Submit - Landscape | REVIEW COMPLETED | |||
04/10/2024 | OK to Submit - Zoning | REVIEW COMPLETED | |||
04/18/2024 | ROW Engineering Review | REVIEW COMPLETED | No Comments David Stiffey David.Stiffey@tucsonaz.gov |