Plan Review Detail
Plan Number: CIP-1025-00026
Parcel: 132030010
Review Status: Requires Resubmit
Review Details: CIP - DEVELOPMENT SITE - INITIAL v.1
Plan Number - CIP-1025-00026
Review Name: CIP - DEVELOPMENT SITE - INITIAL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| NPPO | APPROVED | ||||
| Site Engineering | APPROVED | ||||
| Site Landscape | APPROVED | ||||
| External Reviewers - Tucson Electric Power (TEP) | REQUIRES RESUBMIT | November 6, 2025 WO#T167022 City of Tucson Planning and Development Services Attn: CDRC Admin Team Dear CDRC Admin Team Subject: 100-Acre Wood Bike Park CIP-1025-00026 Tucson Electric Power Company (TEP) has reviewed and cannot approve the development plan submitted 10/17/2025. There are no existing facilities within the development.NO APPARENT CONFLICTS Further: 50' TEP Easement not shown on development plan. Bike paths/improvement within easement area. We would require information on any changes to grade such as berms, bike jumps, etc within our easement area. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer. To apply for electric service, please call the New Construction department at (520) 918- 8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans. If easements are required, they will be secured by separate instrument. Should you have any easement questions, please contact our Land Resources Department, LandReviews@tep.com. Should you have any technical questions, please contact the area designer, Martin Salazar (520) 305-6713 msalazar@tep.com Sincerely, Design Admins Design Admins Tucson Electric Power |
|||
| CDRC Post Review Express | REVIEW COMPLETED | TEP was not approved and will need to see it once again. Also a dust permit will be required based on the Acres of disturbance. If any of the following apply, a Fugitive Dust Activity Permit is required from the Pima County Department of Environmental Quality (PDEQ). Earthmoving or Land Clearing over 1 acre Trenching over 300 feet for utility installation or repair Road construction over 50 feet Blasting Please contact the following to obtain your permit. Fugitive Dust Activity Permit: Contact Pima County ADEQ at (520) 724-7400 https://www.pima.gov/596/Fugitive-Dust Once received you may upload your permit to the attachment section along with any external reviewer approval letters. If you have any questions regarding this information, please contact Sonya Bermudez at sonya.bermudez@tucsonaz.gov or 520-730-7979. |
|||
| External Reviewers - Arizona Department of Transportation (ADOT) | REVIEW COMPLETED | Good Afternoon, ADOT has no comments on this CIP. Thank you for the opportunity to review. |
|||
| External Reviewers - COT Parks & Recreation | REVIEW COMPLETED | Approved Regarding CIP-1025-00026, The City of Tucson Parks and Recreation Department has no additional requirements for the Project and no further reviews by TPRD are required. Description: 100-acre wood bike park Parcel: 130140200 Regards, Joe Barr Project Manager Tucson Parks and Recreation |
|||
| External Reviewers - Pima Association of Governments | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | |||
| External Reviewers - Southwest Gas | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | |||
| External Reviewers - Tucson Airport Authority | REVIEW COMPLETED | October 26, 2025 Planning and Development Services City of Tucson 201 North Stone Avenue Tucson, AZ. 85701 RE: CIP-1025-00026, 1 st Submittal, 100-Acre Wood Bike Park, 2430 S Swan Rd, Tucson AZ 85711, Received October 17, 2025 To whom this may concern, Thank you for the opportunity to comment on CIP-1025-00026, 1 st Submittal, a development plan for new park improvements at 2430 South Swan Road. This development is located in the S one-half of the S one-half of Section 22, Township 14S, Range 14E and the N.W of the quarter of the N.W. quarter of Section 27, Township 14S, Range 14E, of the Gila and Salt River Meridian. The development site occupies parcel numbers 130-14-0200 and 132-03-0010, covers approximately 54.4 ± acres, and is zoned as Residence 1 Zone (R-1) and Light Industrial Zone (I-1). The nearest major roadway intersection is South Alvernon Way and East 29th Street, approximately 1,225 feet to the northwest of the subject development. This site does lie within FAA Part 77 airspace. The Tucson Airport Authority approves the 1st submittal of this project and is not requiring a resubmittal of this project. Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520- 573-4811. Respectfully, Scott Robidoux, C.M. Manager of Planning cc file |
|||
| External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | |||
| Fire New Construction | REVIEW COMPLETED | No Comment | |||
| New Services/JOC | REVIEW COMPLETED | Tucson Water New Area Development has no new comments on or objections to the 100 Acre Wood Bike Park located at 2430 S. Swan Road. | |||
| ROW Engineering Review | REVIEW COMPLETED | No further comments. Previous comments have been addressed. | |||
| Signs | REVIEW COMPLETED | All signage must be permitted by separate sign permit | |||
| Site Zoning | REVIEW COMPLETED | No comments. | |||
| Storm to Shade Review | REVIEW COMPLETED | ||||
| Traffic Engineering Review | REVIEW COMPLETED | Approval for driveway exception is included in the Engineering Review. Per J. Villezcas his approval addredded the attached RoW exception request | |||
| TW Planning and Engineering Review | REVIEW COMPLETED | I see no conflict just keep in mind Tucson Water Plan No. 1-040-2001 for the above ground water features such as ARVs and our Cathodic Test Station locations serving our 54inch ductile iron transmission main. | |||