Plan Review Detail
Plan Number: CIP-0825-00019
Parcel: 108024280
Review Status: Requires Resubmit
Review Details: CIP - DEV SITE + COMM STRUCTURE - FINAL v.1
Plan Number - CIP-0825-00019
Review Name: CIP - DEV SITE + COMM STRUCTURE - FINAL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| Traffic Engineering Review | APPROVED | TE has no comments on this water project. | |||
| Neighborhood Traffic Mitigation | NOT REQUIRED | ||||
| Real Estate | NOT REQUIRED | No Comments | |||
| TSMR/PDMR - Engineering | NOT REQUIRED | NA | |||
| TSMR/PDMR - Environmental Services | NOT REQUIRED | ||||
| TSMR/PDMR - Zoning | NOT REQUIRED | As the site is located in Unincorporated Pima County, City of Tucson Zoning does not apply. | |||
| Zoning Administration | NOT REQUIRED | ||||
| Zoning Compliance Review | NOT REQUIRED | ||||
| CDRC Post Review Express | REQUIRES RESUBMIT | Please address reviewers comment for the next submittal. | |||
| External Reviewers - Tucson Electric Power (TEP) | REQUIRES RESUBMIT | 4350 E. Irvington Road Post Office Box 711, Tucson, AZ 85702 December 29, 2025 WO#T171766 City of Tucson Planning and Development Services Attn: CDRC Admin Team Dear CDRC Admin Team Subject: Manzanita Reservoir & Booster Station CIP-0825-00019 Tucson Electric Power Company (TEP) has reviewed and cannot approve the development plan submitted 11/13/2025. There are existing facilities within the development which are not depicted upon the plan. May check address , should be 2801 E MANZANITA AVE, PL11 Further: TEP's existing easement needs to be shown with correct recording information - Docket-6008 at Page-896. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer. To apply for electric service, please call the New Construction department at (520) 918- 8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans. If easements are required, they will be secured by separate instrument. Should you have any easement questions, please contact our Land Resources Department, LandReviews@tep.com. Should you have any technical questions, please contact the area designer, Chuck Leon (520) 400-6133 cleon@tep.com Sincerely, Design Admins Design Admins Tucson Electric Power |
|||
| Bldg Permits - Post Review Express | REVIEW COMPLETED | ||||
| Building Official | REVIEW COMPLETED | ||||
| CDRC Application Completeness Express | REVIEW COMPLETED | If any of the following apply, a Fugitive Dust Activity Permit is required from the Pima County Department of Environmental Quality (PDEQ). Earthmoving or Land Clearing over 1 acre Trenching over 300 feet for utility installation or repair Road construction over 50 feet Blasting Please contact the following to obtain your permit. Fugitive Dust Activity Permit: Contact Pima County ADEQ at (520) 724-7400 https://www.pima.gov/596/Fugitive-Dust Once received you may upload your permit to the attachment section along with any external reviewer approval letters. If you have any questions regarding this information, please contact Sonya Bermudez at sonya.bermudez@tucsonaz.gov or 520-730-7979. If any of the following apply, a ***Fugitive Dust Activity Permit is required from the Pima County Department of Environmental Quality (PDEQ). Earthmoving or Land Clearing over 1 acre Trenching over 300 feet for utility installation or repair Road construction over 50 feet Blasting Please contact the following to obtain your permit. Fugitive Dust Activity Permit: Contact Pima County ADEQ at (520) 724-7400 https://www.pima.gov/596/Fugitive-Dust Once received you may upload your permit to the attachment section along with any external reviewer approval letters. If you have any questions regarding this information, please contact Sonya Bermudez at sonya.bermudez@tucsonaz.gov ***Please fill out the additional Info Screen with acres of disturbance. *** CDRC added TEP To review, sent email out to have review completed. |
|||
| Commercial Building | REVIEW COMPLETED | 1. Provide the structural calculations used to design the foundations and masonry retaining walls. 2. Provide statement of special inspections with a site specific schedule of required special inspections and tests. |
|||
| Commercial Electrical | REVIEW COMPLETED | No comments. | |||
| Commercial Mechanical | REVIEW COMPLETED | ||||
| Commercial Plumbing | REVIEW COMPLETED | ||||
| Entitlements | REVIEW COMPLETED | ||||
| External Reviewers - Pima Association of Governments | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | |||
| External Reviewers - Southwest Gas | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | |||
| External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | |||
| Fire New Construction | REVIEW COMPLETED | No Comments | |||
| New Services/JOC | REVIEW COMPLETED | Tucson Water has no objection to the proposed project. No comments at this time. There is no observable impact on the existing potable water distribution main. | |||
| NPPO | REVIEW COMPLETED | ||||
| Outdoor Lighting | REVIEW COMPLETED | No comments. | |||
| PDSD Application Completeness Express | REVIEW COMPLETED | ||||
| ROW Engineering Review | REVIEW COMPLETED | Project is outside COT ROW | |||
| Signs | REVIEW COMPLETED | ||||
| Site Engineering | REVIEW COMPLETED | ||||
| Site Landscape | REVIEW COMPLETED | ||||
| Site Zoning | REVIEW COMPLETED | A development package meeting the requirements of Administrative Manual Section 2-06 is required. | |||
| TSMR/PDMR - Landscape | REVIEW COMPLETED | ||||
| TW Planning and Engineering Review | REVIEW COMPLETED | Plan originated in-house, no submittal review required. | |||
| Water - PDSD | REVIEW COMPLETED | ||||
| Zoning Modifications - DDO | REVIEW COMPLETED | ||||
| Zoning Modifications - IPP | REVIEW COMPLETED | ||||
| Zoning Modifications - MS&R | REVIEW COMPLETED | ||||
| Zoning Modifications - Variance | REVIEW COMPLETED |