Plan Number: CIP-0725-00017
Parcel: 11519004S

Review Status: Approved

Review Details: CIP - DEV SITE + COMM STRUCTURE - FINAL v.1

Plan Number - CIP-0725-00017
Review Name: CIP - DEV SITE + COMM STRUCTURE - FINAL v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
Traffic Engineering Review APPROVED Traffic Engineering would suggest all parking stall markings be white
Neighborhood Traffic Mitigation NOT REQUIRED
Real Estate NOT REQUIRED If any action is required to address property rights (dedications, easements, etc), please contact the Real Estate Division 520-791-4181.
TSMR/PDMR - Engineering NOT REQUIRED
TSMR/PDMR - Environmental Services NOT REQUIRED
Zoning Administration NOT REQUIRED
Zoning Compliance Review NOT REQUIRED
Bldg Permits - Post Review Express REVIEW COMPLETED
Building Official REVIEW COMPLETED
CDRC Application Completeness Express REVIEW COMPLETED CDRC added ADOT, TEP, sent out FYIs to SWG, USPS, PAG.
Commercial Building REVIEW COMPLETED Remove the Preliminary Not For Construction annotation over registrant's stamp on Sheet G300
Please contact me if you have any questions about these comments.
Mark Masek
Plans Examiner – Building Safety
Planning and Development Services | City of Tucson
main 520.837.4994
email mark.masek@tucsonaz.gov
Commercial Electrical REVIEW COMPLETED no comments.
Commercial Mechanical REVIEW COMPLETED Ventilation calculations have been provided for the fitness area; provide ventilation calculations for all of the other occupied areas that are part of this activity. Reference: Sections 401.2 and 401.3, IMC 2018..
Commercial Plumbing REVIEW COMPLETED Provide a cleanout for the existing 4” horizontal drain at the connection of the new waste piping. Reference: Section 708.1.5, IPC 2018.
Entitlements REVIEW COMPLETED
External Reviewers - Arizona Department of Transportation (ADOT) REVIEW COMPLETED Re: URGENT PAST DUE ! PERMIT: CIP-0725-00017 Please Sign-In DUE: 12/11/2025 • 11/26/2025 2:39PM
jgomes@azdot.gov
on behalf of
ADOT SC Traffic Engineering - ADOT
​CDRC​
​Christian Niemi​
Good Morning,
ADOT has no comments on this CIP.
Thank you for the opportunity to review.
External Reviewers - Pima Association of Governments REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required
External Reviewers - Southwest Gas REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required
External Reviewers - Tucson Electric Power (TEP) REVIEW COMPLETED Refer to CIP-1225-00029
External Reviewers - United States Postal Service (USPS) REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required
Fire New Construction REVIEW COMPLETED
New Services/JOC REVIEW COMPLETED Tucson Water has no objections to this Development Package/Remodel
NPPO REVIEW COMPLETED See site landscape comments for NPPO comments.

Thank you.
Chad Keller, RLA
chad.keller@tucsonaz.gov
Outdoor Lighting REVIEW COMPLETED Include the outdoor lumen calculations on the final plans.
PDSD Application Completeness Express REVIEW COMPLETED
ROW Engineering Review REVIEW COMPLETED
Signs REVIEW COMPLETED
Site Engineering REVIEW COMPLETED
Site Landscape REVIEW COMPLETED PER COMMENT PROVIDED DURING A PRE APPLICATION MEETING (TP-PRE-0125-00017), FEBRUARY OF 2025, I STATED THE FOLLOWING.

1. Provide protective fencing at the drip line of the existing trees to the west of the new 571 SF addition. This will protect the tree roots from being compacted which could damage or kill the tree.

2. If the Mesquites are going to be removed due to this remodel, then please provide a NPPO or a NPPO Waiver with your next submittal. Mitigation for the two Mesquites may be required per the NPPO.

Thank you.
Chad Keller, RLA
chad.keller@tucsonaz.gov
Site Zoning REVIEW COMPLETED
TSMR/PDMR - Landscape REVIEW COMPLETED
TSMR/PDMR - Zoning REVIEW COMPLETED
TW Planning and Engineering Review REVIEW COMPLETED On sheet 6 of 7, Ref Note 7 states to protect the existing fire service is to be protected. Ref Note 18 states to "realign" to avoid conflict. Which note would be correct? If the fire service is to be realigned it would be problematic as there is no valve in place to turn off the fire service. A new design would have to reflect additional valves to meet SD-500 sheet 4. ***UPDATE*** Emailed G. Vega (Dibble). Engineer will field fit pad around existing Fire Service water line and change plan accordingly. Changing Status to "Review Completed"
Water - PDSD REVIEW COMPLETED Verify the size of the existing water meter and backflow preventer serving the building and provide the new total water demand.
Zoning Modifications - DDO REVIEW COMPLETED
Zoning Modifications - IPP REVIEW COMPLETED
Zoning Modifications - MS&R REVIEW COMPLETED