Review Status: Approved
Review Details: CIP - DEVELOPMENT SITE - FINAL v.2
Plan Number - CIP-0624-00022
Review Name: CIP - DEVELOPMENT SITE - FINAL v.2
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| CDRC Post Review Express | APPROVED | Please submit all documentation supporting external review approvals(External Reviewers Approval Letters), required permits, and reports to your DP application using your TDC online applicant account. | |||
| NPPO | APPROVED | ||||
| Site Engineering | APPROVED | ||||
| Site Landscape | APPROVED | ||||
| Design Review | NOT REQUIRED | Not an Infill Incentive Districts (IID) project. If the IID is going to be used for redevelopment, please let me know: maria.gayosso@tucsonaz.gov. Thank you. | |||
| External Reviewers - Pima County Addressing | NOT REQUIRED | ||||
| External Reviewers - Southwest Gas | NOT REQUIRED | ||||
| External Reviewers - Tucson Electric Power (TEP) | NOT REQUIRED | ||||
| Historic | NOT REQUIRED | Not an Infill Incentive Districts (IID) project. If the IID is going to be used for redevelopment, please let me know: maria.gayosso@tucsonaz.gov. Thank you. | |||
| Real Estate | NOT REQUIRED | ||||
| ROW Engineering Review | NOT REQUIRED | ||||
| Archeological Sensitivity - Standard | REVIEW COMPLETED | Ground disturbance is limited due to previous disturbances. Site is paved over. | |||
| CDRC Application Completeness Express | REVIEW COMPLETED | ||||
| Commercial Plumbing | REVIEW COMPLETED | ||||
| Entitlements | REVIEW COMPLETED | Not required. | |||
| New Services/JOC | REVIEW COMPLETED | CIP-0624-00022 - CIP - Dev Site - Final v2 - 1701 N ORACLE RD Tucson Water’s New Development Section has no objections to this Capital Improvement Project. Tim Rowe, P.E., Civil Engineer Tucson Water, New Development Section 201 N. Stone Avenue, #2-220 P.O. Box 27210 Tucson, AZ 85726-7210 (520) 837-2106 tim.rowe@tucsonaz.gov |
|||
| Site Zoning | REVIEW COMPLETED | ||||
| Storm to Shade Review | REVIEW COMPLETED | Review complete | |||
| Traffic Engineering Review | REVIEW COMPLETED | No Comments from Traffic Engineering | |||
| TW Planning and Engineering Review | REVIEW COMPLETED | Defer to any comments from New Services for Water comments. No proposed developments would be expected to impact existing water mains within right-of-way areas. | |||
| Water - PDSD | REVIEW COMPLETED |