Plan Number: CIP-0624-00022
Parcel: 11518001A

Review Status: Requires Resubmit

Review Details: CIP - DEVELOPMENT SITE - FINAL v.1

Plan Number - CIP-0624-00022
Review Name: CIP - DEVELOPMENT SITE - FINAL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
Design Review NOT REQUIRED Applicant has not elected to utilize the IID Zoning Option.
External Reviewers - Pima County Addressing NOT REQUIRED
External Reviewers - Southwest Gas NOT REQUIRED
NPPO NOT REQUIRED
Real Estate NOT REQUIRED Please notify the Real Estate Division if any property rights need to be addressed.
CDRC Post Review Express REQUIRES RESUBMIT Resubmittal is required for CIP Final Review due to review approvals and comments left. Please address the following reviews to the next CIP Final Review workflow cycle:
1. Storm to shade review, due to PM not adding to final review cycle for approval.
2. Engineering, has left comments that must be addressed
3. Historic review, must be added due to comments left

Please keep in mind when starting a new submittal PM must start a Bluebeam session for reviewers to review documents. If you have questions please reach out to Sonya or Aaron at CDRC@tucsonaz.gov.
Site Engineering REQUIRES RESUBMIT 1. Include the cut/fill quantities on the grading sheet even if they are 0.
CDRC Application Completeness Express REVIEW COMPLETED
Commercial Plumbing REVIEW COMPLETED
Entitlements REVIEW COMPLETED No rezoning or PAD conditions to consider, no IID option. -GS
External Reviewers - Tucson Electric Power (TEP) REVIEW COMPLETED Greetings,



Tucson Electric Power Co. (TEP) has reviewed the plans submitted on October 10th, 2024, and has no objections. The customer is responsible for compliance with City Ordinances. Please note a jurisdictional permit for any work on a public road right of way where applicable. Easements are required for TEP facilities if not appropriately recorded on the final plat. They will need to be obtained by a separate instrument.





Respectfully,

Tucson Electric Power Co.

Land Resources Department
Historic REVIEW COMPLETED This project is currently undergoing Section 106 consultation due to its federal funding and location within the Miracle Mile Historic District. That is being conducted by the applicant. It is also undergoing cultural clearance through the Historic Preservation office. All of those items need to be completed prior to the beginning of construction. For any questions, please contact PDSDHistoric@tucsonaz.gov.
New Services/JOC REVIEW COMPLETED CIP-0624-00022 - CIP - Dev Site - Final v1 - 1701 N ORACLE RD

Tucson Water’s New Development Section has no developer financed projects in this area that may affect or be affected by this Capital Improvement Project.

Tim Rowe, P.E., Civil Engineer
Tucson Water, New Development Section
201 N. Stone Avenue, #2-220
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106
tim.rowe@tucsonaz.gov
ROW Engineering Review REVIEW COMPLETED review completed in initial workflow with no comments
Site Landscape REVIEW COMPLETED Site Landscape/NPPO Section Comments:

The landscape construction document set includes all of the requested details from the 75% landscape review comments. The plans are complete, sealed and signed by the Landscape Architect of record and are ok for approval.

Thank you.
Chad Keller, RLA
chad.keller@tucsonaz.gov
Site Zoning REVIEW COMPLETED A separate demo permit for the removal of the pool will be required.
Traffic Engineering Review REVIEW COMPLETED No comments
TW Planning and Engineering Review REVIEW COMPLETED Noted that backflow preventer was added along with expanded irrigation system. No visible conflicts with existing water CIP infrastructure.