Plan: TW-PLAN-0426-0112
Plan Details
Status:
Review complete
Type:
TW CIP Planning & Engineering
Apply Date:
04/28/2026
Applicant:
Robin
Description:
Project with CMG drainage to design Bank Protection for the West bank of Finger Rock wash within the La Paloma Reservoir property limits, and to provide a looped maintenance path around the reservoir.
Architects:
- CMG Drainage Engineering, Inc
Contractors:
Plan Reviews
Plan Number - TW-PLAN-0426-0112
Plan Status: Review Complete
Plan Description: Project with CMG drainage to design Bank Protection for the West bank of Finger Rock wash within the La Paloma Reservoir property limits, and to provide a looped maintenance path around the reservoir.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/29/2026 | TWPE 60% Design Review v.1 | APPROVED |