Plan: TR-FTTP-1026-00014
Plan Details
Apply Date:
10/07/2026
Applicant:
Alex
Description:
Installation of HDPE conduit for fiber installation either with Bore or Micro Trench.
Architects:
- EZ Barricade
- Wyyerd Fiber
- Wyyerd Fiber LLC
Contractors:
Outstanding Plan Activity Conditions
Plan Number - TR-FTTP-1026-00014
Plan Description: Installation of HDPE conduit for fiber installation either with Bore or Micro Trench.
| Date | Name | Approved | Comments |
|---|---|---|---|
| 10/13/2026 | 1117 W. NAVAJO ST. | Not Approved | same as Tuttle |
| 10/13/2026 | 211 E DOROTHY LN | Not Approved | 1. Pavement moratorium (Mills dr, Dorothy ln, & Norma ln) 2. FPUP - constructed water course "Stone ave wash" 3. Sun tran |
| 10/13/2026 | 2482 W KIMBERLEY PL (x 2) | Not Approved | 1. archeological 2. sun tran (Kain ave) 3. |
| 10/13/2026 | 3321 N. TUTTLE AVE. | Not Approved | 1. Pavement moratorium (Lind, Tuttle, Navajo, Farr, and Erma streets) 2. "NO NAME" Constructed water course at - FPUP needed for this section. |
| 10/13/2026 | 4357 N STANLEY PL | Not Approved | 1. pavement moratorium (Stanley pl, Radin ave, & 4th ave) 2. FPUP- stone ave wash 3. sun tran |
| 10/13/2026 | N SHAWNEE AVE & W DELANO DR | Not Approved | 1. archeological 2. FPUP needed 3. Pavement moratorium (Delano, Gretchen, Sioux, Shawnee, Iroquois & Fort Lowell) |
Plan Reviews
Plan Number - TR-FTTP-1026-00014
Plan Status: Needs Resubmittal
Plan Description: Installation of HDPE conduit for fiber installation either with Bore or Micro Trench.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/07/2026 | Right of Way Review v.1 | REQUIRES RESUBMIT |