Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan: TP-PRE-0424-00090
Plan Details
Apply Date:
04/09/2024
Applicant:
Andrew
Description:
Developing a utility battery energy storage facility to support the TEP grid - see attached Project Description
Architects:
- Capacity Power Group
Contractors:
Plan Reviews
Plan Number - TP-PRE-0424-00090
Plan Status: Complete
Plan Description: Developing a utility battery energy storage facility to support the TEP grid - see attached Project Description
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/17/2024 | Pre-Application Conference Review v.1 | APPROVED |