Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Details

Apply Date:
01/21/2026
Applicant:
Peter
Description:
COT / El Pueblo Project. 56 units / 5 floors / Type IIIB construction. 9% LIHTC Set aside for 2026. Phase 1 of a 2 phase low income housing project. IID project, Stone Ave Subarea. Figure 5.12-STS-B1 applies.
Architects:
  • Gorman & Company
  • Housing and Community Development
  • Poster Mirto McDonald
Contractors:

Plan Reviews

Plan Number - TP-PRE-0126-00019
Plan Status: In Review
Plan Description: COT / El Pueblo Project. 56 units / 5 floors / Type IIIB construction. 9% LIHTC Set aside for 2026. Phase 1 of a 2 phase low income housing project. IID project, Stone Ave Subarea. Figure 5.12-STS-B1 applies.
Start Date Submittal Complete Date Status  
01/22/2026 Pre-Application Conference Review v.1 IN REVIEW Review Details

Documents

File Name Document Type  
TP-PRE-0126-00019 REVISED PRELIM DES PROF REV 2-6-26.PDF DOCUMENTS VIEW
TP-PRE-0126-00019 PRELIM DES PROF REV 2-3-26.PDF DOCUMENTS VIEW
TP-PRE-0126-00019 PRELIM PLANS 1-21-26.PDF DOCUMENTS VIEW